| 29 Sep | Mechanical (HVAC) | Subcontract | PO-HVAC daywork | Airflow Mechanical Services — daywork, ductwork replacement (V-26034-04 pending) | $18,400.00 |
| 18 Sep | Joinery | Labour | Timesheets w/e 18/09 | Workshop & install labour | $1,804.71 |
| 18 Sep | Partitions & Ceilings | Labour | Timesheets w/e 18/09 | Site labour | $4,979.56 |
| 18 Sep | Demolition & Make Good | Labour | Timesheets w/e 18/09 | Site labour | $1,599.01 |
| 18 Sep | Design & Documentation | Labour | Timesheets w/e 18/09 | Site labour | $636.00 |
| 18 Sep | Preliminaries | Labour | Timesheets w/e 18/09 | PM & supervision | $2,463.35 |
| 18 Sep | Plumbing | Subcontract | PO-5425 · claim 2 | Pipeline Plumbing & Gas — progress claim 2 | $2,399.40 |
| 18 Sep | Mechanical (HVAC) | Subcontract | PO-5424 · claim 2 | Airflow Mechanical Services — progress claim 2 | $17,949.41 |
| 18 Sep | Data & Comms | Subcontract | PO-5423 · claim 2 | Netpoint Data & Comms — progress claim 2 | $3,838.52 |
| 18 Sep | Electrical & Lighting | Subcontract | PO-5422 · claim 2 | Voltline Electrical — progress claim 2 | $19,689.41 |
| 18 Sep | Partitions & Ceilings | Subcontract | PO-5421 · claim 2 | Clearline Glass & Glazing — progress claim 2 | $15,596.00 |
| 18 Sep | Design & Documentation | Subcontract | PO-5420 · claim 2 | Certa Building Certifiers — progress claim 2 | $2,566.28 |
| 18 Sep | Preliminaries | Subcontract | PO-5419 · claim 2 | Binway Waste & Skips — progress claim 2 | $1,225.56 |
| 11 Sep | Joinery | Labour | Timesheets w/e 11/09 | Workshop & install labour | $1,804.75 |
| 11 Sep | Partitions & Ceilings | Labour | Timesheets w/e 11/09 | Site labour | $4,979.53 |
| 11 Sep | Demolition & Make Good | Labour | Timesheets w/e 11/09 | Site labour | $1,599.01 |
| 11 Sep | Design & Documentation | Labour | Timesheets w/e 11/09 | Site labour | $636.00 |
| 11 Sep | Preliminaries | Labour | Timesheets w/e 11/09 | PM & supervision | $2,463.32 |
| 8 Sep | Mechanical (HVAC) | Subcontract | V-26034-03 | Variation works — Fire services — sprinkler head relocation | $3,900.00 |
| 4 Sep | Joinery | Labour | Timesheets w/e 04/09 | Workshop & install labour | $1,804.75 |
| 4 Sep | Partitions & Ceilings | Labour | Timesheets w/e 04/09 | Site labour | $4,979.53 |
| 4 Sep | Demolition & Make Good | Labour | Timesheets w/e 04/09 | Site labour | $1,599.01 |
| 4 Sep | Design & Documentation | Labour | Timesheets w/e 04/09 | Site labour | $636.00 |
| 4 Sep | Preliminaries | Labour | Timesheets w/e 04/09 | PM & supervision | $2,463.32 |
| 1 Sep | Joinery | Labour | V-26034-02 | Variation works — Level 1 kitchen enlarged per client sketch | $7,300.00 |
| 28 Aug | Joinery | Labour | Timesheets w/e 28/08 | Workshop & install labour | $1,804.75 |
| 28 Aug | Partitions & Ceilings | Labour | Timesheets w/e 28/08 | Site labour | $4,979.53 |
| 28 Aug | Demolition & Make Good | Labour | Timesheets w/e 28/08 | Site labour | $1,599.01 |
| 28 Aug | Design & Documentation | Labour | Timesheets w/e 28/08 | Site labour | $636.00 |
| 28 Aug | Preliminaries | Labour | Timesheets w/e 28/08 | PM & supervision | $2,463.32 |
| 21 Aug | Joinery | Labour | Timesheets w/e 21/08 | Workshop & install labour | $1,804.75 |
| 21 Aug | Partitions & Ceilings | Labour | Timesheets w/e 21/08 | Site labour | $4,979.53 |
| 21 Aug | Demolition & Make Good | Labour | Timesheets w/e 21/08 | Site labour | $1,599.01 |
| 21 Aug | Design & Documentation | Labour | Timesheets w/e 21/08 | Site labour | $636.00 |
| 21 Aug | Preliminaries | Labour | Timesheets w/e 21/08 | PM & supervision | $2,463.32 |
| 21 Aug | Plumbing | Subcontract | PO-5425 · claim 1 | Pipeline Plumbing & Gas — progress claim 1 | $1,149.48 |
| 21 Aug | Mechanical (HVAC) | Subcontract | PO-5424 · claim 1 | Airflow Mechanical Services — progress claim 1 | $14,031.26 |
| 21 Aug | Data & Comms | Subcontract | PO-5423 · claim 1 | Netpoint Data & Comms — progress claim 1 | $3,868.63 |
| 21 Aug | Electrical & Lighting | Subcontract | PO-5422 · claim 1 | Voltline Electrical — progress claim 1 | $10,744.13 |
| 21 Aug | Partitions & Ceilings | Subcontract | PO-5421 · claim 1 | Clearline Glass & Glazing — progress claim 1 | $17,837.88 |
| 21 Aug | Design & Documentation | Subcontract | PO-5420 · claim 1 | Certa Building Certifiers — progress claim 1 | $2,140.12 |
| 21 Aug | Preliminaries | Subcontract | PO-5419 · claim 1 | Binway Waste & Skips — progress claim 1 | $749.22 |
| 19 Aug | Demolition & Make Good | Labour | V-26034-01 | Variation works — Asbestos-free confirmation & removal of ceiling sheet | $6,400.00 |
| 14 Aug | Joinery | Labour | Timesheets w/e 14/08 | Workshop & install labour | $1,804.75 |
| 14 Aug | Partitions & Ceilings | Labour | Timesheets w/e 14/08 | Site labour | $4,979.53 |
| 14 Aug | Demolition & Make Good | Labour | Timesheets w/e 14/08 | Site labour | $1,599.01 |
| 14 Aug | Design & Documentation | Labour | Timesheets w/e 14/08 | Site labour | $636.00 |
| 14 Aug | Preliminaries | Labour | Timesheets w/e 14/08 | PM & supervision | $2,463.32 |
| 10 Aug | Partitions & Ceilings | Material | PO-5418 | Knauf Plasterboard — materials delivered | $7,601.00 |
| 7 Aug | Joinery | Labour | Timesheets w/e 07/08 | Workshop & install labour | $1,804.75 |
| 7 Aug | Partitions & Ceilings | Labour | Timesheets w/e 07/08 | Site labour | $4,979.53 |
| 7 Aug | Demolition & Make Good | Labour | Timesheets w/e 07/08 | Site labour | $1,599.01 |
| 7 Aug | Design & Documentation | Labour | Timesheets w/e 07/08 | Site labour | $636.00 |
| 7 Aug | Preliminaries | Labour | Timesheets w/e 07/08 | PM & supervision | $2,463.32 |
| 7 Aug | Joinery | Material | PO-5416 | Hettich Australia — materials delivered | $2,443.30 |
| 5 Aug | Partitions & Ceilings | Material | PO-5417 | Rondo Building Services — materials delivered | $8,650.10 |
| 4 Aug | Joinery | Material | PO-5414 | Polytec — materials delivered | $10,636.00 |
| 3 Aug | Joinery | Material | PO-5415 | Laminex Australia — materials delivered | $4,350.00 |
| 31 Jul | Joinery | Labour | Timesheets w/e 31/07 | Workshop & install labour | $1,804.75 |
| 31 Jul | Partitions & Ceilings | Labour | Timesheets w/e 31/07 | Site labour | $4,979.53 |
| 31 Jul | Demolition & Make Good | Labour | Timesheets w/e 31/07 | Site labour | $1,599.01 |
| 31 Jul | Design & Documentation | Labour | Timesheets w/e 31/07 | Site labour | $636.00 |
| 31 Jul | Preliminaries | Labour | Timesheets w/e 31/07 | PM & supervision | $2,463.32 |