PCF-26034 · Nexa Engineering
Birtinya HQ · 2 Eccles Boulevard, Birtinya QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Next step Sends supply POs and subcontract orders to every supplier and trade.
On Site At risk PM Kurt Lindqvist · Site Dean O'Connell · 27 Jul 2026 → PC 27 Nov 2026 (56 days) · Nexa Engineering · from Q-26122 Existing ductwork above level 1 found non-compliant on strip-out — HVAC variation V-26034-04 with client.
Revised contract
$649,077
$627,077 + $22,000 variations
Forecast cost
$545,828
▼ $23,110 over budget
Forecast margin
15.9%
▼ quoted 19.4% · $103,249
Claimed to date
$277,313
43% of contract · 43% complete
Variations with client
$43,375
2 awaiting approval
Purchase orders & subcontracts
| Order | Supplier | Cost code | Type | Status | Required | ETA | Value | Billed |
| PO-5414 | Polytec | Joinery | Supply | Delivered | 10 Aug | 3 Aug | $10,636 | $10,636 |
| PO-5415 | Laminex Australia | Joinery | Supply | Delivered | 10 Aug | 5 Aug | $4,350 | $4,350 |
| PO-5416 | Hettich Australia | Joinery | Supply | Delivered | 10 Aug | 7 Aug | $2,443 | $2,443 |
| PO-5417 | Rondo Building Services | Partitions & Ceilings | Supply | Delivered | 14 Aug | 5 Aug | $8,650 | $8,650 |
| PO-5418 | Knauf Plasterboard | Partitions & Ceilings | Supply | Delivered | 14 Aug | 7 Aug | $7,601 | $7,601 |
| PO-5412 | B Quiet Acoustic Pods | Acoustic Solutions | Supply | Sent | 2 Nov | 30 Oct | $46,800 | $0 |
| PO-5413 | Autex Acoustics | Acoustic Solutions | Supply | Draft | 2 Nov | — | $6,077 | $0 |
| PO-5410 | Workspace Commercial Furniture | Furniture | Supply | Draft | 10 Nov | — | $70,215 | $0 |
| PO-5411 | Buro Seating | Furniture | Supply | Draft | 10 Nov | — | $28,036 | $0 |
| PO-5419 | Coastal Skip Bins | Preliminaries | Subcontract | Accepted | 27 Jul | 27 Jul | $3,450 | $1,975 |
| PO-5420 | Sunshine Coast Certifiers | Design & Documentation | Subcontract | Complete | 27 Jul | 27 Jul | $4,440 | $4,706 |
| PO-5421 | Coast Glass & Glazing | Partitions & Ceilings | Subcontract | Accepted | 14 Aug | 14 Aug | $31,860 | $33,434 |
| PO-5422 | Coastline Electrical Contracting | Electrical & Lighting | Subcontract | Accepted | 18 Aug | 18 Aug | $50,320 | $30,434 |
| PO-5424 | Maroochy Air Conditioning | Mechanical (HVAC) | Subcontract | Accepted | 21 Aug | 21 Aug | $32,640 | $31,981 |
| PO-5423 | Kawana Data & Comms | Data & Comms | Subcontract | Accepted | 2 Sep | 2 Sep | $15,470 | $7,707 |
| PO-5425 | Nambour Plumbing Services | Plumbing | Subcontract | Accepted | 2 Sep | 2 Sep | $6,200 | $3,549 |
| PO-5427 | Buderim Painting Group | Painting | Subcontract | Accepted | 5 Oct | 5 Oct | $16,422 | $0 |
| PO-5426 | Hinterland Flooring Co. | Floor Finishes | Subcontract | Accepted | 19 Oct | 19 Oct | $40,990 | $0 |
| PO-5428 | SignCraft Sunshine Coast | Signage | Subcontract | Accepted | 10 Nov | 10 Nov | $3,600 | $0 |