Sites active this week
5
14 work packages running
Trades on site
2
subcontractors booked this week
Open defects
9
→ none past due
Diary entries (14 days)
25
2 with issues raised
On site this week · 28 Sep – 4 Oct
PCF-26036 Ocean Street Brewing Co
Level 3, 12 First Avenue, Maroochydore QLD · site lead Cooper Walsh
Joinery installationPrima site crew
Services fit-offVoltline Electrical
SignageSignCraft Signage
Furniture deliveryPrima site crew
PCF-26039 Kawana Waters Accountants
Suite 5, 6 Innovation Parkway, Kawana Waters QLD · site lead Cooper Walsh
Joinery manufactureKunda Park workshop
Services rough-inVoltline Electrical
Partitions, framing and ceilingsPrima site crew
PCF-26031 Coastal Legal Partners
Level 2, 1 Duporth Avenue, Maroochydore QLD · site lead Sam Petrovic
Joinery manufactureKunda Park workshop
Partitions, framing and ceilingsPrima site crew
PCF-26046 Iron Coast Fitness
Level 1, 49 Bulcock Street, Caloundra QLD · site lead Sam Petrovic
Defit, demolition and make goodPrima site crew
Services rough-inVoltline Electrical
Partitions, framing and ceilingsPrima site crew
PCF-26034 Nexa Engineering
2 Eccles Boulevard, Birtinya QLD · site lead Dean O'Connell
Joinery manufactureKunda Park workshop
Partitions, framing and ceilingsPrima site crew
Defects
12 cards · drag between columns
Open 5
DEF-412
Glazed front door needs adjusting — drags on closer
PCF-26039 · Reception
Clearline Glass & Glazing · due 9 Oct
DEF-411
Paint missed behind cool room door
PCF-26036 · Back of house
Brushmark Painting & Decorating · due 8 Oct
DEF-410
Festoon light circuit tripping
PCF-26036 · Deck
Voltline Electrical · due 7 Oct
DEF-407
Scuff on feature wall
PCF-26023 · Waiting room
Brushmark Painting & Decorating · due 5 Oct
DEF-408
Bar top silicone joint lifting
PCF-26036 · Taproom
Kunda Park workshop · due 5 Oct
Drop here
In progress 2
DEF-409
Floor waste falls to wrong side
PCF-26036 · Kitchen
Pipeline Plumbing & Gas · due 6 Oct
DEF-405
Pendant light flickering over table 4
PCF-26019 · Dining
Voltline Electrical · due 2 Oct
Drop here
Fixed 2
DEF-406
Door closer slamming
PCF-26023 · Therapy room 2
Prima site crew · due 5 Oct
DEF-402
Replace two damaged carpet tiles at threshold
PCF-26041 · Tenancy entry
Floorworks Commercial Flooring · due 29 Sep
Drop here
Closed 3
DEF-404
Soft-close hinge not catching on fridge door
PCF-26019 · Bar back
Kunda Park workshop · due 1 Oct
DEF-403
Realign sagging tile run
PCF-26041 · Ceiling grid, east wing
Prima site crew · due 30 Sep
DEF-401
Paint touch-up where furniture removed
PCF-26041 · Level 2 corridor
Brushmark Painting & Decorating · due 28 Sep
Drop here
Site diary
| Date | Job | By | Weather | Crew | Trades on site | Work done | Issues | |
|---|---|---|---|---|---|---|---|---|
| 02 Oct 2026 | PCF-26046 | Sam Petrovic | Fine, 27° | 2 | Voltline Electrical | Services rough-in; Partitions, framing and ceilings — progressing to programme. | — | |
| 02 Oct 2026 | PCF-26036 | Cooper Walsh | Showers, 24° | 4 | Voltline Electrical, SignCraft Signage | Services fit-off; Signage; Furniture delivery — progressing to programme. | — | |
| 02 Oct 2026 | PCF-26031 | Sam Petrovic | Fine, 26° | 2 | Prima crew only | Joinery manufacture — progressing to programme. | Workspace Commercial Furniture advised a one-week delay on Zircon frames. | |
| 01 Oct 2026 | PCF-26039 | Cooper Walsh | Fine, 27° | 2 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 01 Oct 2026 | PCF-26034 | Dean O'Connell | Showers, 24° | 4 | Prima crew only | Joinery manufacture — progressing to programme. | Airflow found more non-compliant duct above L1 — daywork recorded. | |
| 30 Sep 2026 | PCF-26046 | Sam Petrovic | Fine, 28° | 4 | Voltline Electrical | Services rough-in; Partitions, framing and ceilings — progressing to programme. | — | |
| 30 Sep 2026 | PCF-26036 | Cooper Walsh | Fine, 27° | 2 | Voltline Electrical, SignCraft Signage | Services fit-off; Signage; Furniture delivery — progressing to programme. | — | |
| 30 Sep 2026 | PCF-26031 | Sam Petrovic | Showers, 24° | 4 | Prima crew only | Joinery manufacture — progressing to programme. | — | |
| 29 Sep 2026 | PCF-26039 | Cooper Walsh | Fine, 28° | 4 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 29 Sep 2026 | PCF-26034 | Dean O'Connell | Fine, 27° | 2 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 28 Sep 2026 | PCF-26046 | Sam Petrovic | Overcast, 25° | 2 | Prima crew only | Defit, demolition and make good — progressing to programme. | — | |
| 28 Sep 2026 | PCF-26036 | Cooper Walsh | Fine, 28° | 4 | Prima crew only | Joinery installation — progressing to programme. | — | |
| 28 Sep 2026 | PCF-26031 | Sam Petrovic | Fine, 27° | 2 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 25 Sep 2026 | PCF-26039 | Cooper Walsh | Fine, 26° | 4 | Voltline Electrical | Services rough-in; Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 25 Sep 2026 | PCF-26034 | Dean O'Connell | Overcast, 25° | 2 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 24 Sep 2026 | PCF-26046 | Sam Petrovic | Showers, 24° | 2 | Prima crew only | Defit, demolition and make good — progressing to programme. | — | |
| 24 Sep 2026 | PCF-26036 | Cooper Walsh | Fine, 26° | 4 | Prima crew only | Joinery installation — progressing to programme. | — | |
| 24 Sep 2026 | PCF-26031 | Sam Petrovic | Overcast, 25° | 2 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 23 Sep 2026 | PCF-26039 | Cooper Walsh | Showers, 24° | 2 | Voltline Electrical | Services rough-in; Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 23 Sep 2026 | PCF-26034 | Dean O'Connell | Fine, 26° | 4 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 22 Sep 2026 | PCF-26046 | Sam Petrovic | Fine, 27° | 4 | Prima crew only | Defit, demolition and make good — progressing to programme. | — | |
| 22 Sep 2026 | PCF-26036 | Cooper Walsh | Showers, 24° | 2 | Prima crew only | Joinery installation — progressing to programme. | — | |
| 22 Sep 2026 | PCF-26031 | Sam Petrovic | Fine, 26° | 4 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 21 Sep 2026 | PCF-26039 | Cooper Walsh | Fine, 27° | 4 | Voltline Electrical | Services rough-in; Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |
| 21 Sep 2026 | PCF-26034 | Dean O'Connell | Showers, 24° | 2 | Prima crew only | Partitions, framing and ceilings; Joinery manufacture — progressing to programme. | — | |