PCF-26034 · Nexa Engineering

Birtinya HQ · 2 Eccles Boulevard, Birtinya QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
On Site At risk PM Kurt Lindqvist · Site Dean O'Connell · 27 Jul 2026 → PC 27 Nov 2026 (56 days) · Nexa Engineering · from Q-26122
Existing ductwork above level 1 found non-compliant on strip-out — HVAC variation V-26034-04 with client.
Revised contract
$649,077
$627,077 + $22,000 variations
Forecast cost
$545,828
▼ $23,110 over budget
Forecast margin
15.9%
▼ quoted 19.4% · $103,249
Claimed to date
$277,313
43% of contract · 43% complete
Variations with client
$43,375
2 awaiting approval
ScheduleOpen Gantt
TaskTradeStartFinishStatusDelivery
◆ Design sign-off & building approvalPrima crew27 Jul27 JulComplete —
Site establishment & hoardingPrima crew29 Jul3 AugComplete —
Strip out & demolitionPrima crew3 Aug18 AugComplete —
Joinery manufacture (Kunda Park workshop)Prima crew10 Aug12 OctIn progress —
Wall framing & partitionsPrima crew14 Aug9 SepComplete —
Electrical & data rough-inCoastline Electrical Contracting21 Aug14 SepComplete —
Mechanical ductwork & diffusersMaroochy Air Conditioning24 Aug24 SepComplete —
Plumbing rough-inNambour Plumbing Services2 Sep17 SepComplete —
Sheet, set & ceiling gridPrima crew9 Sep5 OctIn progress —
Glazed office frontsCoast Glass & Glazing28 Sep9 OctIn progress —
PaintingBuderim Painting Group5 Oct26 OctNot started —
Joinery installationPrima crew14 Oct2 NovNot started —
Electrical fit-off & lightingCoastline Electrical Contracting26 Oct9 NovNot started —
Floor coveringsHinterland Flooring Co.26 Oct12 NovNot started —
Acoustic panels & podsPrima crew9 Nov23 NovNot started PO-5412 ETA 30 Oct
Furniture delivery & installationPrima crew10 Nov23 NovNot started PO-5410 ETA —
Signage & manifestationSignCraft Sunshine Coast16 Nov23 NovNot started —
◆ Practical completion & handoverPrima crew25 Nov25 NovNot started —