Budget vs actual by cost codeClick a % to update progress · committed = issued orders not yet billed
Cost code
Contract
Variations
Budget
Actual
Committed
Forecast
Variance
% complete
Preliminaries
$50,445
—
$37,878
$21,681
$1,475
$37,878
—
54%
Design & Documentation
$11,586
—
$9,240
$9,794
—
$9,794
−$554
100%
Demolition & Make Good
$16,292
$8,000
$18,468
$19,192
—
$19,192
−$724
100%
Partitions & Ceilings
$109,850
—
$86,090
$89,521
—
$89,521
−$3,431
99%
Joinery
$55,620
$9,125
$48,500
$39,167
—
$48,500
—
57%
Electrical & Lighting
$57,868
—
$50,320
$30,434
$19,886
$50,320
—
54%
Data & Comms
$17,790
—
$15,470
$7,707
$7,763
$15,470
—
47%
Mechanical (HVAC)
$37,536
$4,875
$36,540
$54,281
$659
$54,940
−$18,400
69%
Plumbing
$7,130
—
$6,200
$3,549
$2,651
$6,200
—
54%
Floor Finishes
$47,138
—
$40,990
$0
$40,990
$40,990
—
0%
Painting
$18,885
—
$16,422
$0
$16,422
$16,422
—
0%
Furniture
$125,760
—
$98,251
$0
—
$98,251
—
0%
Acoustic Solutions
$67,037
—
$54,749
$0
$46,800
$54,749
—
0%
Signage
$4,140
—
$3,600
$0
$3,600
$3,600
—
0%
Total
$627,077
$22,000
$522,718
$275,327
$140,247
$545,828
−$23,110
43%
⚠ Design & Documentation forecast $554 over budget.
⚠ Demolition & Make Good forecast $724 over budget.
⚠ Partitions & Ceilings forecast $3,431 over budget.
⚠ Mechanical (HVAC) forecast $18,400 over budget.
↺ V-26034-05 Upgrade task chairs to Buro Elan (×62) — $16,125 with the client 2 days. Approval adds $16,125 to the contract and $12,900 to the budget.
↺ V-26034-04 Replace non-compliant ductwork above Level 1 — $27,250 with the client 8 days. Approval adds $27,250 to the contract and $21,800 to the budget.