Prima

PCF-26034 · Nexa Engineering

Birtinya HQ · 2 Eccles Boulevard, Birtinya QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
On Site At risk PM Kurt Lindqvist · Site Dean O'Connell · 27 Jul 2026 → PC 27 Nov 2026 (56 days) · Nexa Engineering · from Q-26122
Existing ductwork above level 1 found non-compliant on strip-out — HVAC variation V-26034-04 with client.
Revised contract
$649,077
$627,077 + $22,000 variations
Forecast cost
$545,828
▼ $23,110 over budget
Forecast margin
15.9%
▼ quoted 19.4% · $103,249
Claimed to date
$277,313
43% of contract · 43% complete
Variations with client
$43,375
2 awaiting approval
Variations
RefVariationReasonStatusCostPriceRaised
V-26034-05Upgrade task chairs to Buro Elan (×62)
Furniture
Client requestSubmitted$12,900$16,12529 Sep 2026
V-26034-04Replace non-compliant ductwork above Level 1
Mechanical (HVAC)
Latent conditionSubmitted$21,800$27,25023 Sep 2026
V-26034-03Fire services — sprinkler head relocation
Mechanical (HVAC)
Authority requirementApproved$3,900$4,87531 Aug 2026
V-26034-02Level 1 kitchen enlarged per client sketch
Joinery
Client requestApproved$7,300$9,12524 Aug 2026
V-26034-01Asbestos-free confirmation & removal of ceiling sheet
Demolition & Make Good
Latent conditionApproved$6,400$8,00011 Aug 2026