✓ EnquiryENQ-2407 · Website ✓ QuoteQ-26122 · Accepted · $627,077 ✓ Invoicingdeposit on acceptance ✓ ProjectPCF-26034 · On Site 5 Orders3 to issue 6 ScheduleJoinery manufacture 10 Aug 7 Joinery0/4 ready 8 Variations2 with client 9 Costingmargin 15.9% · $277,313 claimed
Next step Sends supply POs and subcontract orders to every supplier and trade.
On Site At risk PM Kurt Lindqvist · Site Dean O'Connell · 27 Jul 2026 → PC 27 Nov 2026 (56 days) · Nexa Engineering · from Q-26122
Existing ductwork above level 1 found non-compliant on strip-out — HVAC variation V-26034-04 with client.
Revised contract
$649,077
$627,077 + $22,000 variations
Forecast cost
$545,828
▼ $23,110 over budget
Forecast margin
15.9%
▼ quoted 19.4% · $103,249
Claimed to date
$277,313
43% of contract · 43% complete
Variations with client
$43,375
2 awaiting approval