Replace non-compliant ductwork above Level 1
SubmittedReplace non-compliant ductwork above Level 1. Scope, pricing and schedule impact as per attached.
- Project
- PCF-26034 Nexa Engineering — Birtinya HQ
- Reason
- Latent condition
- Cost code
- Mechanical (HVAC)
- Our cost
- $21,800.00
- Price (ex GST)
- $27,250.00 · 20% margin
- Price (inc GST)
- $29,975.00
- Schedule impact
- 6 working days
- Raised
- 23 Sep 2026 by Kurt Lindqvist
- Submitted
- 24 Sep 2026 · 8 days with client
- Decision
- —
Client approval
Paul Ferreira approves from a link — no login. The decision lands here, in notifications and on the job costing straight away.
Prima Commercial Fitouts Pty Ltd · Unit 4, 15 Page Street, Kunda Park QLD 4556
ABN 38 010 662 911 · QBCC Lic. 1038827 · (07) 5473 9055 · info@primacommercial.com.au
Variation
V-26034-04
Date 24 Sep 2026
Project PCF-26034
Client
Nexa Engineering
Paul Ferreira
2 Eccles Boulevard, Birtinya QLD
Replace non-compliant ductwork above Level 1
Replace non-compliant ductwork above Level 1. Scope, pricing and schedule impact as per attached.
| Subtotal (ex GST) | $27,250.00 |
| GST 10% | $2,725.00 |
| Total (inc GST) | $29,975.00 |
Reason: Latent condition. Schedule impact: 6 working days.
Approved variations are added to the contract sum and claimed with the next progress claim.
Approved by: ______________________ Date: ____________