Live jobs96 under way · 3 starting soon
This week14work packages running · 4 subcontracted
Needs attention4late delivery · out of sequence · double-booking · over capacity
Joinery workshop peak110%w/c 26 Oct · site crew peak 82%
9 jobs · click a job to expand
21 Sep
This week
5 Oct
12 Oct
19 Oct
26 Oct
2 Nov
9 Nov
16 Nov
23 Nov
30 Nov
7 Dec
Joinery workshop114 h a week · 3 joiners
92%
92%
92%
66%
66%
110%
44%
44%
70%
26%
26%
0%
Site crew228 h a week · 6 carpenters & labourers
81%
51%
33%
34%
46%
50%
82%
72%
37%
9%
16%
35%
Calculated from the in-house hours on the work packages below — move a package and capacity recalculates.
Today
▸ PCF-26041 Tidewater Property Group Kurt · 99% complete · handover 25 Sep Handed over — closing out defects
end-of-lease make good · 99%
1Site handover and establishment
✓ Site handover and establishment · done 1 Sep
2Defit, demolition and make good
✓ Defit, demolition and make good · done 7 Sep
6Flooring
✓ Flooring · done 18 Sep
7Painting
✓ Painting · done 18 Sep
14Final clean, defects and handover
Final clean, defects and handover · Prima crew
▸ PCF-26036 Ocean Street Brewing Co Jess · 81% complete · handover 16 Oct Now: Joinery installation, Services fit-off +2
1Site handover and establishment
✓ Site handover and establishment · done 24 Jul
2Defit, demolition and make good
✓ Defit, demolition and make good · done 6 Aug
3Services rough-in
✓ Services rough-in · done 24 Aug
4Partitions, framing and ceilings
✓ Partitions, framing and ceilings · done 7 Sep
5Joinery manufacture
✓ Joinery manufacture · done 11 Sep
6Flooring
Flooring · Floorworks
7Painting
Painting · Brushmark
8Joinery installation
Joinery installation · Prima crew
9Services fit-off
Services fit-off · Voltline
11Signage
Signage · SignCraft
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · Prima crew
▸ PCF-26039 Kawana Waters Accountants Jess · 42% complete · handover 30 Oct ⚠ Out of sequence
1Site handover and establishment
✓ Site handover and establishment · done 9 Sep
2Defit, demolition and make good
✓ Defit, demolition and make good · done 15 Sep
3Services rough-in
Services rough-in · Voltline
4Partitions, framing and ceilings
Partitions, framing and ceilings · Prima crew
5Joinery manufacture
Joinery manufacture · Workshop
6Flooring
Flooring · Tread
7Painting
Painting · Truecoat
8Joinery installation
Joinery installation · Prima crew
9Services fit-off
⚠ Services fit-off · Voltline
10Glazing and doors
Glazing and doors · Paneview
11Signage
Signage · SignCraft
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · Prima crew
▸ PCF-26044 STEPS Staffing Solutions Kurt · 1% complete · handover 6 Nov Starts 19 Oct
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · Prima crew
▸ PCF-26031 Coastal Legal Partners Kurt · 42% complete · handover 13 Nov ⚠ Late delivery
1Site handover and establishment
✓ Site handover and establishment · done 14 Aug
3Services rough-in
✓ Services rough-in · done 14 Sep
4Partitions, framing and ceilings
Partitions, framing and ceilings · Prima crew
5Joinery manufacture
Joinery manufacture · Workshop
6Flooring
Flooring · Floorworks
7Painting
⚠ Painting · Brushmark
8Joinery installation
Joinery installation · Prima crew
9Services fit-off
Services fit-off · Voltline
10Glazing and doors
Glazing and doors · Clearline
11Signage
Signage · SignCraft
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
⚠ Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · Prima crew
▸ PCF-26046 Iron Coast Fitness Kurt · 21% complete · handover 20 Nov Now: Defit, demolition and make good, Services rough-in +1
1Site handover and establishment
✓ Site handover and establishment · done 17 Sep
2Defit, demolition and make good
Defit, demolition and make good · Prima crew
3Services rough-in
Services rough-in · Voltline
4Partitions, framing and ceilings
Partitions, framing and ceilings · Prima crew
5Joinery manufacture
Joinery manufacture · Workshop
6Flooring
Flooring · Floorworks
7Painting
Painting · Truecoat
8Joinery installation
Joinery installation · Prima crew
9Services fit-off
Services fit-off · Voltline
11Signage
Signage · SignCraft
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · Prima crew
▸ PCF-26034 Nexa Engineering Kurt · 43% complete · handover 27 Nov ⚠ Subcontractor double-booked
1Site handover and establishment
✓ Site handover and establishment · done 3 Aug
2Defit, demolition and make good
✓ Defit, demolition and make good · done 18 Aug
3Services rough-in
✓ Services rough-in · done 11 Sep
4Partitions, framing and ceilings
Partitions, framing and ceilings · Prima crew
5Joinery manufacture
6Flooring
Flooring · Floorworks
7Painting
8Joinery installation
Joinery installation · Prima crew
9Services fit-off
Services fit-off · Voltline
10Glazing and doors
Glazing and doors · Clearline
11Signage
Signage · SignCraft
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · Prima crew
▸ PCF-26047 Peregian Realty Jess · 2% complete · handover 11 Dec Starts 26 Oct
1Site handover and establishment
Site handover and establishment · Prima crew
3Services rough-in
Services rough-in · Livewire
4Partitions, framing and ceilings
Partitions, framing and ceilings · Prima crew
5Joinery manufacture
Joinery manufacture · Workshop
6Flooring
Flooring · Floorworks
7Painting
Painting · Truecoat
8Joinery installation
Joinery installation · Prima crew
9Services fit-off
Services fit-off · Livewire
10Glazing and doors
Glazing and doors · Clearline
11Signage
Signage · SignCraft
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · from 14 Dec →
▸ PCF-26042 Arthur Care Jess · 2% complete · handover 18 Dec Starts 12 Oct
1Site handover and establishment
Site handover and establishment · Prima crew
3Services rough-in
Services rough-in · Livewire
4Partitions, framing and ceilings
Partitions, framing and ceilings · Prima crew
5Joinery manufacture
6Flooring
Flooring · Floorworks
7Painting
Painting · Brushmark
8Joinery installation
Joinery installation · Prima crew
9Services fit-off
Services fit-off · Livewire
10Glazing and doors
Glazing and doors · Clearline
11Signage
Signage · SignCraft
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · from 15 Dec →
Click a job to see its work packages · drag a package to move it, drag its right edge to change its length · click a package to edit or reassign it.