Prima

PCF-26039 · Kawana Waters Accountants

make good & refresh · Suite 5, 6 Innovation Parkway, Kawana Waters QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
On Site On track PM Jess Moreland · Site Cooper Walsh · 07 Sep 2026 → PC 30 Oct 2026 (28 days) · Kawana Waters Accountants · from Q-26128
Revised contract
$211,421
$209,771 + $1,650 variations
Forecast cost
$170,215
▲ within budget $170,215
Forecast margin
19.5%
▲ quoted 19.5% · $41,207
Claimed to date
$81,077
38% of contract · 42% complete
Variations with client
$0
0 awaiting approval
Budget vs actual by cost code Click a % to update progress · committed = issued orders not yet billed
Cost codeContractVariationsBudgetActualCommittedForecastVariance% complete
Preliminaries $17,984 — $13,628 $6,341 $1,107 $13,628 —
47%
Design & Documentation $7,183 — $5,778 $5,720 $31 $5,778 —
100%
Demolition & Make Good $7,136 — $5,286 $5,233 — $5,286 —
100%
Partitions & Ceilings $39,775 — $31,386 $26,011 $2,700 $31,386 —
80%
Joinery $28,391 — $21,030 $14,025 — $21,030 —
48%
Electrical & Lighting $19,573 — $17,020 $7,245 $9,775 $17,020 —
43%
Data & Comms $6,070 — $5,278 $1,724 $3,554 $5,278 —
33%
Mechanical (HVAC) $12,696 — $11,040 $5,902 $5,138 $11,040 —
54%
Plumbing $7,130 — $6,200 $2,332 $3,868 $6,200 —
38%
Floor Finishes $15,985 — $13,900 $0 $13,900 $13,900 —
0%
Painting $6,388 $1,650 $6,875 $0 $5,555 $6,875 —
0%
Furniture $33,739 — $26,359 $0 $26,359 $26,359 —
0%
Acoustic Solutions $3,581 — $2,835 $0 $1,899 $2,835 —
0%
Signage $4,140 — $3,600 $0 $3,600 $3,600 —
0%
Total$209,771$1,650$170,215 $74,535$77,484$170,215 —42%