Prima

PCF-26042 · Arthur Care

Sippy Downs clinic · Unit 3, 10 Chancellor Village Boulevard, Sippy Downs QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Pre-construction On track PM Jess Moreland · Site Sam Petrovic · 12 Oct 2026 → PC 18 Dec 2026 (77 days) · Arthur Care · from Q-26134
Revised contract
$182,257
$182,257 + $0 variations
Forecast cost
$148,154
▲ within budget $148,154
Forecast margin
18.7%
▲ quoted 18.7% · $34,103
Claimed to date
$18,226
10% of contract · 2% complete
Variations with client
$0
0 awaiting approval
Budget vs actual by cost code Click a % to update progress · committed = issued orders not yet billed
Cost codeContractVariationsBudgetActualCommittedForecastVariance% complete
Preliminaries $18,113 — $13,724 $124 $1,946 $13,724 —
6%
Design & Documentation $7,217 — $5,808 $1,248 $1,872 $5,808 —
40%
Partitions & Ceilings $40,614 — $32,008 $0 $12,980 $32,008 —
0%
Joinery $22,383 — $16,580 $0 $982 $16,580 —
0%
Electrical & Lighting $20,424 — $17,760 $0 $17,760 $17,760 —
0%
Data & Comms $3,140 — $2,730 $0 $2,730 $2,730 —
0%
Mechanical (HVAC) $13,248 — $11,520 $0 $11,520 $11,520 —
0%
Plumbing $11,040 — $9,600 $0 $9,600 $9,600 —
0%
Floor Finishes $16,646 — $14,475 $0 $14,475 $14,475 —
0%
Painting $6,665 — $5,796 $0 $5,796 $5,796 —
0%
Furniture $16,019 — $12,515 $0 — $12,515 —
0%
Acoustic Solutions $2,608 — $2,038 $0 — $2,038 —
0%
Signage $4,140 — $3,600 $0 $3,600 $3,600 —
0%
Total$182,257$0$148,154 $1,372$83,261$148,154 —2%