PCF-26042 · Arthur Care
Sippy Downs clinic · Unit 3, 10 Chancellor Village Boulevard, Sippy Downs QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Next step Sends supply POs and subcontract orders to every supplier and trade.
Pre-construction On track PM Jess Moreland · Site Sam Petrovic · 12 Oct 2026 → PC 18 Dec 2026 (77 days) · Arthur Care · from Q-26134 Revised contract
$182,257
$182,257 + $0 variations
Forecast cost
$148,154
▲ within budget $148,154
Forecast margin
18.7%
▲ quoted 18.7% · $34,103
Claimed to date
$18,226
10% of contract · 2% complete
Variations with client
$0
0 awaiting approval
| Task | Trade | Start | Finish | Status | Delivery |
| Site handover and establishment | Prima site crew | 12 Oct | 15 Oct | Not started | — |
| Services rough-in | Livewire Electrical | 23 Oct | 5 Nov | Not started | — |
| Partitions, framing and ceilings | Prima site crew | 23 Oct | 16 Nov | Not started | — |
| Joinery manufacture | Kunda Park workshop | 26 Oct | 20 Nov | Not started | — |
| Flooring | Floorworks Commercial Flooring | 23 Nov | 30 Nov | Not started | — |
| Painting | Brushmark Painting & Decorating | 23 Nov | 30 Nov | Not started | — |
| Glazing and doors | Clearline Glass & Glazing | 23 Nov | 30 Nov | Not started | — |
| Joinery installation | Prima site crew | 30 Nov | 7 Dec | Not started | — |
| Signage | SignCraft Signage | 7 Dec | 9 Dec | Not started | — |
| Furniture delivery | Prima site crew | 7 Dec | 7 Dec | Not started | — |
| Services fit-off | Livewire Electrical | 8 Dec | 11 Dec | Not started | — |
| Furniture installation | Prima site crew | 8 Dec | 14 Dec | Not started | PO-5467 ETA — |
| Final clean, defects and handover | Prima site crew | 15 Dec | 18 Dec | Not started | — |