Prima

PCF-26042 · Arthur Care

Sippy Downs clinic · Unit 3, 10 Chancellor Village Boulevard, Sippy Downs QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Pre-construction On track PM Jess Moreland · Site Sam Petrovic · 12 Oct 2026 → PC 18 Dec 2026 (77 days) · Arthur Care · from Q-26134
Revised contract
$182,257
$182,257 + $0 variations
Forecast cost
$148,154
▲ within budget $148,154
Forecast margin
18.7%
▲ quoted 18.7% · $34,103
Claimed to date
$18,226
10% of contract · 2% complete
Variations with client
$0
0 awaiting approval
Actual costs posted$1,372
DateCost codeTypeSourceDescriptionAmount
29 SepDesign & DocumentationSubcontractPO-5476 · claim 1Certa Building Certifiers — progress claim 1$1,248.00
29 SepPreliminariesSubcontractPO-5475 · claim 1Binway Waste & Skips — progress claim 1$124.20