Every live job · 21 Sep – 15 Nov 2026
Demo 02 Oct 2026
Live jobs96 under way · 3 starting soon
This week14work packages running · 4 subcontracted
Needs attention4late delivery · out of sequence · double-booking · over capacity
Joinery workshop peak110%w/c 26 Oct · site crew peak 82%
CompleteIn progressNot startedAt risk In-houseSubcontractorPO delivery
1 job · click a job to expand
21 Sep
This week
5 Oct
12 Oct
19 Oct
26 Oct
2 Nov
9 Nov
Joinery workshop114 h a week · 3 joiners
92%
92%
92%
66%
66%
110%
44%
44%
Site crew228 h a week · 6 carpenters & labourers
81%
51%
33%
34%
46%
50%
82%
72%
Calculated from the in-house hours on the work packages below — move a package and capacity recalculates.
Today
▸ PCF-26042 Arthur Care Jess · 2% complete · handover 18 Dec Starts 12 Oct
Sippy Downs clinic · 2%
1Site handover and establishment Prima site crew
Site handover and establishment · Prima crew
3Services rough-in Livewire Electricalafter site handover and establishment
Services rough-in · Livewire
4Partitions, framing and ceilings Prima site crewafter site handover and establishment
Partitions, framing and ceilings · Prima crew
5Joinery manufacture Kunda Park workshopafter site handover and establishment
Joinery manufacture · Workshop
6Flooring Floorworks Commercial Flooringafter partitions
Flooring · from 23 Nov →
7Painting Brushmark Painting & Decoratingafter partitions
Painting · from 23 Nov →
8Joinery installation Prima site crewafter joinery manufacture
Joinery installation · from 30 Nov →
9Services fit-off Livewire Electricalafter joinery installation
Services fit-off · from 8 Dec →
10Glazing and doors Clearline Glass & Glazingafter partitions
Glazing and doors · from 23 Nov →
11Signage SignCraft Signageafter painting
Signage · from 7 Dec →
12Furniture delivery Prima site crewafter flooring
Furniture delivery · from 7 Dec →
13Furniture installation Prima site crewafter furniture delivery
Furniture installation · from 8 Dec →
14Final clean, defects and handover Prima site crewafter furniture installation
Final clean, defects and handover · from 15 Dec →
Click a job to see its work packages · drag a package to move it, drag its right edge to change its length · click a package to edit or reassign it.