Prima

PCF-26042 · Arthur Care

Sippy Downs clinic · Unit 3, 10 Chancellor Village Boulevard, Sippy Downs QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Pre-construction On track PM Jess Moreland · Site Sam Petrovic · 12 Oct 2026 → PC 18 Dec 2026 (77 days) · Arthur Care · from Q-26134
Revised contract
$182,257
$182,257 + $0 variations
Forecast cost
$148,154
▲ within budget $148,154
Forecast margin
18.7%
▲ quoted 18.7% · $34,103
Claimed to date
$18,226
10% of contract · 2% complete
Variations with client
$0
0 awaiting approval
Purchase orders & subcontracts
OrderSupplierCost codeTypeStatusRequiredETAValueBilled
PO-5470PolytecJoinerySupplyDraft19 Oct—$4,202$0
PO-5471Laminex AustraliaJoinerySupplyDraft19 Oct—$1,450$0
PO-5472Hettich AustraliaJoinerySupplySent19 Oct12 Oct$982$0
PO-5473Rondo Building ServicesPartitions & CeilingsSupplyDraft22 Oct—$3,023$0
PO-5474Knauf PlasterboardPartitions & CeilingsSupplyDraft22 Oct—$2,649$0
PO-5469Autex AcousticsAcoustic SolutionsSupplyDraft7 Dec—$1,102$0
PO-5467Buro SeatingFurnitureSupplyDraft9 Dec—$6,465$0
PO-5468Workspace Commercial FurnitureFurnitureSupplyDraft9 Dec—$6,050$0
PO-5475Binway Waste & SkipsPreliminariesSubcontractAccepted12 Oct12 Oct$2,070$124
PO-5476Certa Building CertifiersDesign & DocumentationSubcontractAccepted12 Oct12 Oct$3,120$1,248
PO-5477Clearline Glass & GlazingPartitions & CeilingsSubcontractAccepted22 Oct22 Oct$12,980$0
PO-5478Livewire ElectricalElectrical & LightingSubcontractAccepted26 Oct26 Oct$17,760$0
PO-5480Airflow Mechanical ServicesMechanical (HVAC)SubcontractAccepted26 Oct26 Oct$11,520$0
PO-5479Netpoint Data & CommsData & CommsSubcontractAccepted2 Nov2 Nov$2,730$0
PO-5481Pipeline Plumbing & GasPlumbingSubcontractAccepted2 Nov2 Nov$9,600$0
PO-5483Brushmark Painting & DecoratingPaintingSubcontractAccepted18 Nov18 Nov$5,796$0
PO-5482Floorworks Commercial FlooringFloor FinishesSubcontractAccepted27 Nov27 Nov$14,475$0
PO-5484SignCraft SignageSignageSubcontractAccepted9 Dec9 Dec$3,600$0