✓ EnquiryENQ-2413 · LinkedIn ✓ QuoteQ-26140 · Accepted · $289,103 3 Invoicingdeposit on acceptance ✓ ProjectPCF-26046 · On Site 5 Orders3 to issue 6 ScheduleServices rough-in 29 Sep 7 Joinery0/2 ready 8 Variations0 approved 9 Costingmargin 18.8% · $51,878 claimed
Next step Sends supply POs and subcontract orders to every supplier and trade.
On Site On track PM Kurt Lindqvist · Site Sam Petrovic · 14 Sep 2026 → PC 20 Nov 2026 (49 days) · Iron Coast Fitness · from Q-26140
Revised contract
$289,103
$289,103 + $0 variations
Forecast cost
$234,776
▲ within budget $234,776
Forecast margin
18.8%
▲ quoted 18.8% · $54,327
Claimed to date
$51,878
18% of contract · 21% complete
Variations with client
$0
0 awaiting approval