PCF-26046 · Iron Coast Fitness
Caloundra gym fitout · Level 1, 49 Bulcock Street, Caloundra QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Next step Sends supply POs and subcontract orders to every supplier and trade.
On Site On track PM Kurt Lindqvist · Site Sam Petrovic · 14 Sep 2026 → PC 20 Nov 2026 (49 days) · Iron Coast Fitness · from Q-26140 Revised contract
$289,103
$289,103 + $0 variations
Forecast cost
$234,776
▲ within budget $234,776
Forecast margin
18.8%
▲ quoted 18.8% · $54,327
Claimed to date
$51,878
18% of contract · 21% complete
Variations with client
$0
0 awaiting approval
Actual costs posted$51,095
| Date | Cost code | Type | Source | Description | Amount |
| 2 Oct | Joinery | Labour | Timesheets w/e 02/10 | Workshop & install labour | $894.90 |
| 2 Oct | Partitions & Ceilings | Labour | Timesheets w/e 02/10 | Site labour | $2,030.70 |
| 2 Oct | Demolition & Make Good | Labour | Timesheets w/e 02/10 | Site labour | $3,217.34 |
| 2 Oct | Design & Documentation | Labour | Timesheets w/e 02/10 | Site labour | $1,344.00 |
| 2 Oct | Preliminaries | Labour | Timesheets w/e 02/10 | PM & supervision | $2,244.78 |
| 29 Sep | Mechanical (HVAC) | Subcontract | PO-5502 · claim 1 | Airflow Mechanical Services — progress claim 1 | $3,494.40 |
| 29 Sep | Electrical & Lighting | Subcontract | PO-5500 · claim 1 | Voltline Electrical — progress claim 1 | $5,002.40 |
| 29 Sep | Design & Documentation | Subcontract | PO-5499 · claim 1 | Certa Building Certifiers — progress claim 1 | $3,960.00 |
| 29 Sep | Preliminaries | Subcontract | PO-5498 · claim 1 | Binway Waste & Skips — progress claim 1 | $745.20 |
| 25 Sep | Joinery | Labour | Timesheets w/e 25/09 | Workshop & install labour | $894.90 |
| 25 Sep | Partitions & Ceilings | Labour | Timesheets w/e 25/09 | Site labour | $2,030.70 |
| 25 Sep | Demolition & Make Good | Labour | Timesheets w/e 25/09 | Site labour | $3,217.33 |
| 25 Sep | Design & Documentation | Labour | Timesheets w/e 25/09 | Site labour | $1,344.00 |
| 25 Sep | Preliminaries | Labour | Timesheets w/e 25/09 | PM & supervision | $2,244.78 |
| 21 Sep | Partitions & Ceilings | Material | PO-5496 | Rondo Building Services — materials delivered | $4,666.70 |
| 18 Sep | Joinery | Labour | Timesheets w/e 18/09 | Workshop & install labour | $894.90 |
| 18 Sep | Partitions & Ceilings | Labour | Timesheets w/e 18/09 | Site labour | $2,030.70 |
| 18 Sep | Demolition & Make Good | Labour | Timesheets w/e 18/09 | Site labour | $3,217.33 |
| 18 Sep | Design & Documentation | Labour | Timesheets w/e 18/09 | Site labour | $1,344.00 |
| 18 Sep | Preliminaries | Labour | Timesheets w/e 18/09 | PM & supervision | $2,244.78 |
| 18 Sep | Partitions & Ceilings | Material | PO-5497 | Knauf Plasterboard — materials delivered | $4,031.00 |