On Site On track PM Kurt Lindqvist · Site Sam Petrovic · 14 Sep 2026 → PC 20 Nov 2026 (49 days) · Iron Coast Fitness · from Q-26140
Revised contract
$289,103
$289,103 + $0 variations
Forecast cost
$234,776
▲ within budget $234,776
Forecast margin
18.8%
▲ quoted 18.8% · $54,327
Claimed to date
$51,878
18% of contract · 21% complete
Variations with client
$0
0 awaiting approval
Actual costs posted$51,095
DateCost codeTypeSourceDescriptionAmount
2 OctJoineryLabourTimesheets w/e 02/10Workshop & install labour$894.90
2 OctPartitions & CeilingsLabourTimesheets w/e 02/10Site labour$2,030.70
2 OctDemolition & Make GoodLabourTimesheets w/e 02/10Site labour$3,217.34
2 OctDesign & DocumentationLabourTimesheets w/e 02/10Site labour$1,344.00
2 OctPreliminariesLabourTimesheets w/e 02/10PM & supervision$2,244.78
29 SepMechanical (HVAC)SubcontractPO-5502 · claim 1Airflow Mechanical Services — progress claim 1$3,494.40
29 SepElectrical & LightingSubcontractPO-5500 · claim 1Voltline Electrical — progress claim 1$5,002.40
29 SepDesign & DocumentationSubcontractPO-5499 · claim 1Certa Building Certifiers — progress claim 1$3,960.00
29 SepPreliminariesSubcontractPO-5498 · claim 1Binway Waste & Skips — progress claim 1$745.20
25 SepJoineryLabourTimesheets w/e 25/09Workshop & install labour$894.90
25 SepPartitions & CeilingsLabourTimesheets w/e 25/09Site labour$2,030.70
25 SepDemolition & Make GoodLabourTimesheets w/e 25/09Site labour$3,217.33
25 SepDesign & DocumentationLabourTimesheets w/e 25/09Site labour$1,344.00
25 SepPreliminariesLabourTimesheets w/e 25/09PM & supervision$2,244.78
21 SepPartitions & CeilingsMaterialPO-5496Rondo Building Services — materials delivered$4,666.70
18 SepJoineryLabourTimesheets w/e 18/09Workshop & install labour$894.90
18 SepPartitions & CeilingsLabourTimesheets w/e 18/09Site labour$2,030.70
18 SepDemolition & Make GoodLabourTimesheets w/e 18/09Site labour$3,217.33
18 SepDesign & DocumentationLabourTimesheets w/e 18/09Site labour$1,344.00
18 SepPreliminariesLabourTimesheets w/e 18/09PM & supervision$2,244.78
18 SepPartitions & CeilingsMaterialPO-5497Knauf Plasterboard — materials delivered$4,031.00