PCF-26046 · Iron Coast Fitness
Caloundra gym fitout · Level 1, 49 Bulcock Street, Caloundra QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Next step Sends supply POs and subcontract orders to every supplier and trade.
On Site On track PM Kurt Lindqvist · Site Sam Petrovic · 14 Sep 2026 → PC 20 Nov 2026 (49 days) · Iron Coast Fitness · from Q-26140 Revised contract
$289,103
$289,103 + $0 variations
Forecast cost
$234,776
▲ within budget $234,776
Forecast margin
18.8%
▲ quoted 18.8% · $54,327
Claimed to date
$51,878
18% of contract · 21% complete
Variations with client
$0
0 awaiting approval
| Task | Trade | Start | Finish | Status | Delivery |
| Site handover and establishment | Prima site crew | 14 Sep | 17 Sep | Complete | — |
| Defit, demolition and make good | Prima site crew | 18 Sep | 28 Sep | Complete | — |
| Services rough-in | Voltline Electrical | 29 Sep | 12 Oct | In progress | — |
| Partitions, framing and ceilings | Prima site crew | 29 Sep | 23 Oct | In progress | — |
| Joinery manufacture | Kunda Park workshop | 12 Oct | 30 Oct | Not started | — |
| Flooring | Floorworks Commercial Flooring | 26 Oct | 2 Nov | Not started | — |
| Painting | Truecoat Painting Services | 26 Oct | 2 Nov | Not started | — |
| Joinery installation | Prima site crew | 2 Nov | 9 Nov | Not started | — |
| Signage | SignCraft Signage | 9 Nov | 11 Nov | Not started | — |
| Furniture delivery | Prima site crew | 9 Nov | 9 Nov | Not started | — |
| Services fit-off | Voltline Electrical | 10 Nov | 13 Nov | Not started | — |
| Furniture installation | Prima site crew | 10 Nov | 16 Nov | Not started | PO-5491 ETA — |
| Final clean, defects and handover | Prima site crew | 17 Nov | 20 Nov | Not started | — |