Prima

Quote Q-26140

Iron Coast Fitness — Caloundra gym fitout
Demo 02 Oct 2026
Quote total (ex GST)
$289,103
$318,013.30 inc GST
Estimated cost
$234,776
24 lines · 14 cost codes
Margin
18.8%
$54,327 gross profit
Mix
Furniture Material Labour Subcontract
Estimate Accepted
DescriptionTypeQtyUnit costMarkupCostSell
Preliminaries$27,702$36,846
Site establishment, amenities & floor protection Labour 1 lot $4,000.00 35% $4,000 $5,400
Project management & site supervision Labour 7 wk $2,650.00 35% $18,550 $25,043
Skip bins & waste removal
Binway Waste & Skips
Subcontract 4 ea $690.00 15% $2,760 $3,174
Final builders clean & handover Labour 520 m² $4.60 35% $2,392 $3,229
Design & Documentation$7,992$9,997
Workspace design — concept, layout & finishes schedule Labour 42 hr $96.00 35% $4,032 $5,443
Building approval & certification (Certa Building Certifiers)
Certa Building Certifiers
Subcontract 1 lot $3,960.00 15% $3,960 $4,554
Demolition & Make Good$9,652$13,030
Strip out partitions, ceilings & services to agreed scope Labour 182 m² $26.00 35% $4,732 $6,388
Make good slab, walls & penetrations Labour 1 lot $4,920.00 35% $4,920 $6,642
Partitions & Ceilings$29,010$39,163
Plasterboard partitions — 92mm steel stud, acoustic insulated, set & sanded Labour 31 lm $238.00 35% $7,378 $9,960
Suspended ceiling 1200×600 — fine fissured tile, new grid Labour 338 m² $64.00 35% $21,632 $29,203
Joinery$21,040$28,404
Reception counter — Polytec Ravine Natural Oak, Essastone top, DDA section Labour 1 ea $11,200.00 35% $11,200 $15,120
Staff kitchenette — overheads, island bench, Essastone tops Labour 6 lm $1,640.00 35% $9,840 $13,284
Electrical & Lighting$38,480$44,252
Electrical — power to layout, LED panel & feature lighting, switchboard upgrade
Voltline Electrical
Subcontract 520 m² $74.00 15% $38,480 $44,252
Data & Comms$6,006$6,907
Cat6A data outlets, patching & comms cabinet
Netpoint Data & Comms
Subcontract 33 pt $182.00 15% $6,006 $6,907
Mechanical (HVAC)$24,960$28,704
Mechanical — ductwork modifications, diffusers & re-balance
Airflow Mechanical Services
Subcontract 520 m² $48.00 15% $24,960 $28,704
Plumbing$6,200$7,130
Plumbing — kitchenette sink, Zip HydroTap & HWS
Pipeline Plumbing & Gas
Subcontract 1 lot $6,200.00 15% $6,200 $7,130
Floor Finishes$35,386$40,693
Interface carpet tiles — supply & lay, incl. floor prep
Floorworks Commercial Flooring
Subcontract 130 m² $61.00 15% $7,930 $9,119
Rubber gym flooring 15mm — supply & lay
Floorworks Commercial Flooring
Subcontract 312 m² $88.00 15% $27,456 $31,574
Painting$12,558$14,442
Paint walls, ceilings & doors — Dulux Wash&Wear, 2 coats
Brushmark Painting & Decorating
Subcontract 1,092 m² $11.50 15% $12,558 $14,442
Furniture$8,710$11,149
Reception stool, swivel, gas lift — Black
Buro Seating
Furniture 4 ea $175.00 28% $700 $896
Personal lockers, 12-door bank, keyless — White / oak doors
Workspace Commercial Furniture
Furniture 3 bank $1,750.00 28% $5,250 $6,720
Lounge chair, single, curved back — Terracotta boucle
Buro Seating
Furniture 4 ea $690.00 28% $2,760 $3,533
Acoustic Solutions$3,480$4,246
Autex Cube acoustic wall panel 12mm — Assorted
Autex Acoustics
Material 60 m² $58.00 22% $3,480 $4,246
Signage$3,600$4,140
Reception wall sign (3D acrylic) & glazing manifestation
SignCraft Signage
Subcontract 1 lot $3,600.00 15% $3,600 $4,140
Subtotal (ex GST)$234,776$289,103.00
GST 10%$28,910.30
Total (inc GST)$318,013.30
Client
Zac Pemberton · zac@ironcoastfitness.com.au
Level 1, 49 Bulcock Street, Caloundra QLD
Estimator: Marcus Reid · Quoted 06 Aug 2026 · Valid to 05 Sep 2026
Client approval

Accepted on 13 Aug 2026 — project raised.

Open project PCF-26046 →
Cost codes
Preliminaries$36,846 · 25%
Design & Documentation$9,997 · 20%
Demolition & Make Good$13,030 · 26%
Partitions & Ceilings$39,163 · 26%
Joinery$28,404 · 26%
Electrical & Lighting$44,252 · 13%
Data & Comms$6,907 · 13%
Mechanical (HVAC)$28,704 · 13%
Plumbing$7,130 · 13%
Floor Finishes$40,693 · 13%
Painting$14,442 · 13%
Furniture$11,149 · 22%
Acoustic Solutions$4,246 · 18%
Signage$4,140 · 13%