✓ EnquiryENQ-2413 · LinkedIn ✓ QuoteQ-26140 · Accepted · $289,103 3 Invoicingdeposit on acceptance ✓ ProjectPCF-26046 · On Site 5 Orders3 to issue 6 ScheduleServices rough-in 29 Sep 7 Joinery0/2 ready 8 Variations0 approved 9 Costingmargin 18.8% · $51,878 claimed
Next step Sends supply POs and subcontract orders to every supplier and trade.
Quote total (ex GST)
$289,103
$318,013.30 inc GST
Estimated cost
$234,776
24 lines · 14 cost codes
Margin
18.8%
$54,327 gross profit
Mix
Furniture Material Labour Subcontract
Client
Zac Pemberton · zac@ironcoastfitness.com.au
Level 1, 49 Bulcock Street, Caloundra QLD
Estimator: Marcus Reid · Quoted 06 Aug 2026 · Valid to 05 Sep 2026
Cost codes
Preliminaries$36,846 · 25%
Design & Documentation$9,997 · 20%
Demolition & Make Good$13,030 · 26%
Partitions & Ceilings$39,163 · 26%
Joinery$28,404 · 26%
Electrical & Lighting$44,252 · 13%
Data & Comms$6,907 · 13%
Mechanical (HVAC)$28,704 · 13%
Plumbing$7,130 · 13%
Floor Finishes$40,693 · 13%
Painting$14,442 · 13%
Furniture$11,149 · 22%
Acoustic Solutions$4,246 · 18%
Signage$4,140 · 13%
Prima Commercial Fitouts Pty Ltd · Unit 4, 15 Page Street, Kunda Park QLD 4556
ABN 38 010 662 911 · QBCC Lic. 1038827 · (07) 5473 9055 · info@primacommercial.com.au
Quotation
Q-26140
Date 06 Aug 2026
Valid until 05 Sep 2026
Estimator Marcus Reid
Client
Iron Coast Fitness
Zac Pemberton
Level 1, 49 Bulcock Street, Caloundra QLD
ABN 62 415 343 653
Caloundra gym fitout
| Scope | Amount (ex GST) |
|---|---|
| Preliminaries Site establishment, amenities & floor protection · Project management & site supervision · Skip bins & waste removal · Final builders clean & handover | $36,846.00 |
| Design & Documentation Workspace design · Building approval & certification (Certa Building Certifiers) | $9,997.00 |
| Demolition & Make Good Strip out partitions, ceilings & services to agreed scope · Make good slab, walls & penetrations | $13,030.00 |
| Partitions & Ceilings Plasterboard partitions · Suspended ceiling 1200×600 | $39,163.00 |
| Joinery Reception counter · Staff kitchenette | $28,404.00 |
| Electrical & Lighting Electrical | $44,252.00 |
| Data & Comms Cat6A data outlets, patching & comms cabinet | $6,907.00 |
| Mechanical (HVAC) Mechanical | $28,704.00 |
| Plumbing Plumbing | $7,130.00 |
| Floor Finishes Interface carpet tiles · Rubber gym flooring 15mm | $40,693.00 |
| Painting Paint walls, ceilings & doors | $14,442.00 |
| Furniture Reception stool, swivel, gas lift · Personal lockers, 12-door bank, keyless · Lounge chair, single, curved back | $11,149.00 |
| Acoustic Solutions Autex Cube acoustic wall panel 12mm | $4,246.00 |
| Signage Reception wall sign (3D acrylic) & glazing manifestation | $4,140.00 |
| Subtotal (ex GST) | $289,103.00 |
| GST 10% | $28,910.30 |
| Total (inc GST) | $318,013.30 |
Fixed-price quotation for the scope described. Prices exclude GST unless stated. Deposit of 10% on acceptance, progress claims monthly on works completed. Variations by written approval only.
Exclusions: authority fees, after-hours work unless noted, asbestos removal.