PCF-26039 · Kawana Waters Accountants
make good & refresh · Suite 5, 6 Innovation Parkway, Kawana Waters QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Next step % complete + approved variations, less retention.
Revised contract
$211,421
$209,771 + $1,650 variations
Forecast cost
$170,215
▲ within budget $170,215
Forecast margin
19.5%
▲ quoted 19.5% · $41,207
Claimed to date
$81,077
38% of contract · 42% complete
Variations with client
$0
0 awaiting approval
| Task | Trade | Start | Finish | Status | Delivery |
| Site handover and establishment | Prima site crew | 7 Sep | 9 Sep | Complete | — |
| Defit, demolition and make good | Prima site crew | 10 Sep | 15 Sep | Complete | — |
| Joinery manufacture | Kunda Park workshop | 10 Sep | 9 Oct | In progress | — |
| Services rough-in | Voltline Electrical | 16 Sep | 28 Sep | Complete | — |
| Partitions, framing and ceilings | Prima site crew | 16 Sep | 5 Oct | In progress | — |
| Flooring | Tread Flooring Contractors | 9 Oct | 14 Oct | Not started | — |
| Painting | Truecoat Painting Services | 9 Oct | 15 Oct | Not started | — |
| Glazing and doors | Paneview Glazing | 12 Oct | 14 Oct | Not started | — |
| Joinery installation | Prima site crew | 16 Oct | 19 Oct | Not started | — |
| Services fit-off | Voltline Electrical | 16 Oct | 22 Oct | At risk | — |
| Signage | SignCraft Signage | 20 Oct | 23 Oct | Not started | — |
| Furniture delivery | Prima site crew | 20 Oct | 22 Oct | Not started | — |
| Furniture installation | Prima site crew | 23 Oct | 28 Oct | Not started | PO-5446 ETA 19 Oct |
| Final clean, defects and handover | Prima site crew | 29 Oct | 2 Nov | Not started | — |