✓ EnquiryENQ-2409 · Google ✓ QuoteQ-26128 · Accepted · $209,771 3 Invoicingdeposit on acceptance ✓ ProjectPCF-26039 · On Site 5 Orders5/8 delivered 6 ScheduleJoinery manufacture 14 Sep 7 Joinery0/4 ready ✓ Variations1 approved 9 Costingmargin 19.5% · $81,077 claimed
Next step % complete + approved variations, less retention.
On Site On track PM Jess Moreland · Site Cooper Walsh · 07 Sep 2026 → PC 30 Oct 2026 (28 days) · Kawana Waters Accountants · from Q-26128
Revised contract
$211,421
$209,771 + $1,650 variations
Forecast cost
$170,215
▲ within budget $170,215
Forecast margin
19.5%
▲ quoted 19.5% · $41,207
Claimed to date
$81,077
38% of contract · 42% complete
Variations with client
$0
0 awaiting approval