✓ EnquiryENQ-2406 · Referral ✓ QuoteQ-26119 · Accepted · $387,739 ✓ Invoicingdeposit on acceptance ✓ ProjectPCF-26031 · On Site 5 Orders1 to issue 6 ScheduleJoinery manufacture 20 Aug 7 Joinery0/4 ready 8 Variations1 with client 9 Costingmargin 19.4% · $173,889 claimed
Next step Sends supply POs and subcontract orders to every supplier and trade.
On Site On track PM Kurt Lindqvist · Site Sam Petrovic · 10 Aug 2026 → PC 13 Nov 2026 (42 days) · Coastal Legal Partners · from Q-26119
Revised contract
$402,814
$387,739 + $15,075 variations
Forecast cost
$324,793
▲ within budget $324,793
Forecast margin
19.4%
▲ quoted 19.3% · $78,021
Claimed to date
$173,889
43% of contract · 42% complete
Variations with client
$1,225
1 awaiting approval