PCF-26023 · Eloff & Andrews

consulting rooms · Suite 2, 9 Main Street, Buderim QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Defects Liability On track PM Jess Moreland · Site Cooper Walsh · 01 Jun 2026 → PC 21 Aug 2026 · Eloff & Andrews Clinical Psychology · from Q-26116
Revised contract
$174,380
$168,255 + $6,125 variations
Forecast cost
$141,451
▲ within budget $141,451
Forecast margin
18.9%
▲ quoted 18.8% · $32,930
Claimed to date
$174,380
100% of contract · 100% complete
Variations with client
$0
0 awaiting approval
Actual costs posted$140,016
DateCost codeTypeSourceDescriptionAmount
18 SepSignageSubcontractPO-5390 · claim 4SignCraft Signage — progress claim 4$387.10
18 SepPaintingSubcontractPO-5389 · claim 4Brushmark Painting & Decorating — progress claim 4$517.65
18 SepFloor FinishesSubcontractPO-5388 · claim 4Floorworks Commercial Flooring — progress claim 4$2,172.95
18 SepPlumbingSubcontractPO-5387 · claim 4Pipeline Plumbing & Gas — progress claim 4$1,349.20
18 SepMechanical (HVAC)SubcontractPO-5386 · claim 4Airflow Mechanical Services — progress claim 4$1,433.65
18 SepData & CommsSubcontractPO-5385 · claim 4Netpoint Data & Comms — progress claim 4$414.05
18 SepElectrical & LightingSubcontractPO-5384 · claim 4Voltline Electrical — progress claim 4$2,369.50
18 SepPartitions & CeilingsSubcontractPO-5383 · claim 4Clearline Glass & Glazing — progress claim 4$2,219.79
18 SepDesign & DocumentationSubcontractPO-5382 · claim 4Certa Building Certifiers — progress claim 4$494.14
18 SepPreliminariesSubcontractPO-5381 · claim 4Binway Waste & Skips — progress claim 4$311.60
21 AugSignageSubcontractPO-5390 · claim 3SignCraft Signage — progress claim 3$533.48
21 AugPaintingSubcontractPO-5389 · claim 3Brushmark Painting & Decorating — progress claim 3$753.04
21 AugFloor FinishesSubcontractPO-5388 · claim 3Floorworks Commercial Flooring — progress claim 3$1,394.17
21 AugPlumbingSubcontractPO-5387 · claim 3Pipeline Plumbing & Gas — progress claim 3$1,534.46
21 AugMechanical (HVAC)SubcontractPO-5386 · claim 3Airflow Mechanical Services — progress claim 3$1,984.85
21 AugData & CommsSubcontractPO-5385 · claim 3Netpoint Data & Comms — progress claim 3$248.62
21 AugElectrical & LightingSubcontractPO-5384 · claim 3Voltline Electrical — progress claim 3$2,193.35
21 AugPartitions & CeilingsSubcontractPO-5383 · claim 3Clearline Glass & Glazing — progress claim 3$3,012.81
21 AugDesign & DocumentationSubcontractPO-5382 · claim 3Certa Building Certifiers — progress claim 3$267.95
21 AugPreliminariesSubcontractPO-5381 · claim 3Binway Waste & Skips — progress claim 3$154.02
6 AugFurnitureMaterialPO-5374Workspace Commercial Furniture — delivery$5,460.00
4 AugFurnitureMaterialPO-5373Buro Seating — delivery$6,070.00
3 AugAcoustic SolutionsMaterialPO-5375Autex Acoustics — delivery$986.00
24 JulAcoustic SolutionsLabourTimesheets w/e 24/07Site labour$106.92
24 JulJoineryLabourTimesheets w/e 24/07Workshop & install labour$1,190.03
24 JulPartitions & CeilingsLabourTimesheets w/e 24/07Site labour$1,460.48
24 JulDesign & DocumentationLabourTimesheets w/e 24/07Site labour$320.76
24 JulPreliminariesLabourTimesheets w/e 24/07PM & supervision$1,406.56
24 JulSignageSubcontractPO-5390 · claim 2SignCraft Signage — progress claim 2$515.29
24 JulPaintingSubcontractPO-5389 · claim 2Brushmark Painting & Decorating — progress claim 2$917.11
24 JulFloor FinishesSubcontractPO-5388 · claim 2Floorworks Commercial Flooring — progress claim 2$3,372.11
24 JulPlumbingSubcontractPO-5387 · claim 2Pipeline Plumbing & Gas — progress claim 2$1,575.55
24 JulMechanical (HVAC)SubcontractPO-5386 · claim 2Airflow Mechanical Services — progress claim 2$1,722.17
24 JulData & CommsSubcontractPO-5385 · claim 2Netpoint Data & Comms — progress claim 2$921.56
24 JulElectrical & LightingSubcontractPO-5384 · claim 2Voltline Electrical — progress claim 2$5,017.74
24 JulPartitions & CeilingsSubcontractPO-5383 · claim 2Clearline Glass & Glazing — progress claim 2$2,338.66
24 JulDesign & DocumentationSubcontractPO-5382 · claim 2Certa Building Certifiers — progress claim 2$806.58
24 JulPreliminariesSubcontractPO-5381 · claim 2Binway Waste & Skips — progress claim 2$560.47
17 JulAcoustic SolutionsLabourTimesheets w/e 17/07Site labour$106.92
17 JulJoineryLabourTimesheets w/e 17/07Workshop & install labour$1,190.03
17 JulPartitions & CeilingsLabourTimesheets w/e 17/07Site labour$1,460.50
17 JulDesign & DocumentationLabourTimesheets w/e 17/07Site labour$320.76
17 JulPreliminariesLabourTimesheets w/e 17/07PM & supervision$1,406.54
10 JulAcoustic SolutionsLabourTimesheets w/e 10/07Site labour$106.92
10 JulJoineryLabourTimesheets w/e 10/07Workshop & install labour$1,190.03
10 JulPartitions & CeilingsLabourTimesheets w/e 10/07Site labour$1,460.50
10 JulDesign & DocumentationLabourTimesheets w/e 10/07Site labour$320.76
10 JulPreliminariesLabourTimesheets w/e 10/07PM & supervision$1,406.54
7 JulPartitions & CeilingsLabourV-26023-01Variation works — Acoustic upgrade to therapy room walls (Rw 50)$4,900.00
3 JulAcoustic SolutionsLabourTimesheets w/e 03/07Site labour$106.92
3 JulJoineryLabourTimesheets w/e 03/07Workshop & install labour$1,190.03
3 JulPartitions & CeilingsLabourTimesheets w/e 03/07Site labour$1,460.50
3 JulDesign & DocumentationLabourTimesheets w/e 03/07Site labour$320.76
3 JulPreliminariesLabourTimesheets w/e 03/07PM & supervision$1,406.54
26 JunAcoustic SolutionsLabourTimesheets w/e 26/06Site labour$106.92
26 JunJoineryLabourTimesheets w/e 26/06Workshop & install labour$1,190.03
26 JunPartitions & CeilingsLabourTimesheets w/e 26/06Site labour$1,460.50
26 JunDesign & DocumentationLabourTimesheets w/e 26/06Site labour$320.76
26 JunPreliminariesLabourTimesheets w/e 26/06PM & supervision$1,406.54
26 JunSignageSubcontractPO-5390 · claim 1SignCraft Signage — progress claim 1$2,128.13
26 JunPaintingSubcontractPO-5389 · claim 1Brushmark Painting & Decorating — progress claim 1$2,832.99
26 JunFloor FinishesSubcontractPO-5388 · claim 1Floorworks Commercial Flooring — progress claim 1$5,549.62
26 JunPlumbingSubcontractPO-5387 · claim 1Pipeline Plumbing & Gas — progress claim 1$5,044.79
26 JunMechanical (HVAC)SubcontractPO-5386 · claim 1Airflow Mechanical Services — progress claim 1$4,838.53
26 JunData & CommsSubcontractPO-5385 · claim 1Netpoint Data & Comms — progress claim 1$758.11
26 JunElectrical & LightingSubcontractPO-5384 · claim 1Voltline Electrical — progress claim 1$5,804.01
26 JunPartitions & CeilingsSubcontractPO-5383 · claim 1Clearline Glass & Glazing — progress claim 1$4,110.74
26 JunDesign & DocumentationSubcontractPO-5382 · claim 1Certa Building Certifiers — progress claim 1$1,431.03
26 JunPreliminariesSubcontractPO-5381 · claim 1Binway Waste & Skips — progress claim 1$1,023.21
19 JunAcoustic SolutionsLabourTimesheets w/e 19/06Site labour$106.92
19 JunJoineryLabourTimesheets w/e 19/06Workshop & install labour$1,190.03
19 JunPartitions & CeilingsLabourTimesheets w/e 19/06Site labour$1,460.50
19 JunDesign & DocumentationLabourTimesheets w/e 19/06Site labour$320.76
19 JunPreliminariesLabourTimesheets w/e 19/06PM & supervision$1,406.54
12 JunAcoustic SolutionsLabourTimesheets w/e 12/06Site labour$106.92
12 JunJoineryLabourTimesheets w/e 12/06Workshop & install labour$1,190.03
12 JunPartitions & CeilingsLabourTimesheets w/e 12/06Site labour$1,460.50
12 JunDesign & DocumentationLabourTimesheets w/e 12/06Site labour$320.76
12 JunPreliminariesLabourTimesheets w/e 12/06PM & supervision$1,406.54
10 JunPartitions & CeilingsMaterialPO-5379Rondo Building Services — materials delivered$2,686.00
8 JunPartitions & CeilingsMaterialPO-5380Knauf Plasterboard — materials delivered$2,387.00
8 JunJoineryMaterialPO-5377Laminex Australia — materials delivered$1,450.00
5 JunAcoustic SolutionsLabourTimesheets w/e 05/06Site labour$106.92
5 JunJoineryLabourTimesheets w/e 05/06Workshop & install labour$1,190.03
5 JunPartitions & CeilingsLabourTimesheets w/e 05/06Site labour$1,460.50
5 JunDesign & DocumentationLabourTimesheets w/e 05/06Site labour$320.76
5 JunPreliminariesLabourTimesheets w/e 05/06PM & supervision$1,406.54
4 JunJoineryMaterialPO-5376Polytec — materials delivered$4,202.00
1 JunJoineryMaterialPO-5378Hettich Australia — materials delivered$982.00