PCF-26047 · Peregian Realty
Peregian Beach sales office · Shop 1, 220 David Low Way, Peregian Beach QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Next step Sends supply POs and subcontract orders to every supplier and trade.
Pre-construction On track PM Jess Moreland · Site Cooper Walsh · 26 Oct 2026 → PC 11 Dec 2026 (70 days) · Peregian Realty · from Q-26143 Revised contract
$131,144
$131,144 + $0 variations
Forecast cost
$106,204
▲ within budget $106,204
Forecast margin
19.0%
▲ quoted 19.0% · $24,940
Claimed to date
$13,114
10% of contract · 2% complete
Variations with client
$0
0 awaiting approval
| Task | Trade | Start | Finish | Status | Delivery |
| Site handover and establishment | Prima site crew | 26 Oct | 28 Oct | Not started | — |
| Services rough-in | Livewire Electrical | 3 Nov | 12 Nov | Not started | — |
| Partitions, framing and ceilings | Prima site crew | 3 Nov | 18 Nov | Not started | — |
| Joinery manufacture | Kunda Park workshop | 16 Nov | 4 Dec | Not started | — |
| Flooring | Floorworks Commercial Flooring | 23 Nov | 27 Nov | Not started | — |
| Painting | Truecoat Painting Services | 23 Nov | 30 Nov | Not started | — |
| Glazing and doors | Clearline Glass & Glazing | 24 Nov | 27 Nov | Not started | — |
| Signage | SignCraft Signage | 2 Dec | 7 Dec | Not started | — |
| Furniture delivery | Prima site crew | 3 Dec | 4 Dec | Not started | — |
| Joinery installation | Prima site crew | 7 Dec | 9 Dec | Not started | — |
| Furniture installation | Prima site crew | 7 Dec | 11 Dec | Not started | PO-5507 ETA — |
| Services fit-off | Livewire Electrical | 10 Dec | 15 Dec | Not started | — |
| Final clean, defects and handover | Prima site crew | 14 Dec | 16 Dec | Not started | — |