PCF-26047 · Peregian Realty

Peregian Beach sales office · Shop 1, 220 David Low Way, Peregian Beach QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Pre-construction On track PM Jess Moreland · Site Cooper Walsh · 26 Oct 2026 → PC 11 Dec 2026 (70 days) · Peregian Realty · from Q-26143
Revised contract
$131,144
$131,144 + $0 variations
Forecast cost
$106,204
▲ within budget $106,204
Forecast margin
19.0%
▲ quoted 19.0% · $24,940
Claimed to date
$13,114
10% of contract · 2% complete
Variations with client
$0
0 awaiting approval
ScheduleOpen Gantt
TaskTradeStartFinishStatusDelivery
Site handover and establishmentPrima site crew26 Oct28 OctNot started —
Services rough-inLivewire Electrical3 Nov12 NovNot started —
Partitions, framing and ceilingsPrima site crew3 Nov18 NovNot started —
Joinery manufactureKunda Park workshop16 Nov4 DecNot started —
FlooringFloorworks Commercial Flooring23 Nov27 NovNot started —
PaintingTruecoat Painting Services23 Nov30 NovNot started —
Glazing and doorsClearline Glass & Glazing24 Nov27 NovNot started —
SignageSignCraft Signage2 Dec7 DecNot started —
Furniture deliveryPrima site crew3 Dec4 DecNot started —
Joinery installationPrima site crew7 Dec9 DecNot started —
Furniture installationPrima site crew7 Dec11 DecNot started PO-5507 ETA —
Services fit-offLivewire Electrical10 Dec15 DecNot started —
Final clean, defects and handoverPrima site crew14 Dec16 DecNot started —