PCF-26036 · Ocean Street Brewing Co
taproom & kitchen · Level 3, 12 First Avenue, Maroochydore QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Next step Variation waiting on client approval.
Revised contract
$258,358
$252,420 + $5,938 variations
Forecast cost
$207,841
▲ within budget $207,841
Forecast margin
19.6%
▲ quoted 19.5% · $50,517
Claimed to date
$201,769
78% of contract · 81% complete
Variations with client
$3,000
1 awaiting approval
Purchase orders & subcontracts
| Order | Supplier | Cost code | Type | Status | Required | ETA | Value | Billed |
| PO-5432 | Polytec | Joinery | Supply | Delivered | 29 Jul | 23 Jul | $10,684 | $10,684 |
| PO-5433 | Laminex Australia | Joinery | Supply | Delivered | 29 Jul | 22 Jul | $4,350 | $4,350 |
| PO-5434 | Hettich Australia | Joinery | Supply | Delivered | 29 Jul | 23 Jul | $2,443 | $2,443 |
| PO-5435 | Rondo Building Services | Partitions & Ceilings | Supply | Delivered | 3 Aug | 27 Jul | $2,563 | $2,563 |
| PO-5436 | Knauf Plasterboard | Partitions & Ceilings | Supply | Delivered | 3 Aug | 27 Jul | $2,230 | $2,230 |
| PO-5431 | Autex Acoustics | Acoustic Solutions | Supply | Confirmed | 28 Sep | 25 Sep | $6,912 | $0 |
| PO-5429 | Workspace Commercial Furniture | Furniture | Supply | Sent | 5 Oct | 1 Oct | $6,540 | $0 |
| PO-5430 | Buro Seating | Furniture | Supply | Sent | 5 Oct | 28 Sep | $8,880 | $0 |
| PO-5437 | Binway Waste & Skips | Preliminaries | Subcontract | Accepted | 20 Jul | 20 Jul | $2,070 | $1,687 |
| PO-5438 | Certa Building Certifiers | Design & Documentation | Subcontract | Complete | 20 Jul | 20 Jul | $3,180 | $3,085 |
| PO-5439 | Voltline Electrical | Electrical & Lighting | Subcontract | Accepted | 5 Aug | 5 Aug | $23,920 | $22,506 |
| PO-5441 | Airflow Mechanical Services | Mechanical (HVAC) | Subcontract | Complete | 7 Aug | 7 Aug | $17,680 | $17,150 |
| PO-5440 | Netpoint Data & Comms | Data & Comms | Subcontract | Complete | 17 Aug | 17 Aug | $2,912 | $2,825 |
| PO-5442 | Pipeline Plumbing & Gas | Plumbing | Subcontract | Complete | 17 Aug | 17 Aug | $18,400 | $17,848 |
| PO-5444 | Brushmark Painting & Decorating | Painting | Subcontract | Accepted | 7 Sep | 7 Sep | $6,279 | $5,725 |
| PO-5443 | Floorworks Commercial Flooring | Floor Finishes | Subcontract | Accepted | 18 Sep | 18 Sep | $16,640 | $11,783 |
| PO-5445 | SignCraft Signage | Signage | Subcontract | Accepted | 5 Oct | 5 Oct | $7,800 | $0 |