PCF-26011 · Kairos Community College

learning hub · 8 Enterprise Street, Kunda Park QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Closed On track PM Jess Moreland · Site Sam Petrovic · 09 Mar 2026 → PC 26 Jun 2026 · Kairos Community College · from Q-26110
Revised contract
$251,336
$248,361 + $2,975 variations
Forecast cost
$204,100
▼ $504 over budget
Forecast margin
18.8%
▼ quoted 19.0% · $47,236
Claimed to date
$251,336
100% of contract · 100% complete
Variations with client
$0
0 awaiting approval
Budget vs actual by cost code Click a % to update progress · committed = issued orders not yet billed
Cost codeContractVariationsBudgetActualCommittedForecastVariance% complete
Preliminaries $26,564 — $19,984 $19,584 $41 $19,984 —
100%
Design & Documentation $8,210 — $6,588 $6,456 $68 $6,588 —
100%
Partitions & Ceilings $56,799 — $44,696 $44,006 $354 $44,696 —
100%
Joinery $29,565 — $21,900 $22,404 — $22,404 −$504
100%
Electrical & Lighting $28,934 — $25,160 $24,657 $503 $25,160 —
100%
Data & Comms $4,395 $2,975 $6,202 $6,126 $76 $6,202 —
100%
Mechanical (HVAC) $18,768 — $16,320 $15,994 $326 $16,320 —
100%
Plumbing $7,130 — $6,200 $6,076 $124 $6,200 —
100%
Floor Finishes $23,570 — $20,495 $20,085 $410 $20,495 —
100%
Painting $9,443 — $8,211 $8,047 $164 $8,211 —
100%
Furniture $23,900 — $18,672 $18,672 — $18,672 —
100%
Acoustic Solutions $6,943 — $5,568 $5,545 — $5,568 —
100%
Signage $4,140 — $3,600 $3,528 $72 $3,600 —
100%
Total$248,361$2,975$203,596 $201,179$2,140$204,100 −$504100%
⚠ Joinery forecast $504 over budget.