Prima

Quote Q-26110

Kairos Community College — learning hub
Demo 02 Oct 2026
Quote total (ex GST)
$248,361
$273,197.10 inc GST
Estimated cost
$201,216
27 lines · 13 cost codes
Margin
19.0%
$47,145 gross profit
Mix
Furniture Material Labour Subcontract
Estimate Accepted
DescriptionTypeQtyUnit costMarkupCostSell
Preliminaries$19,984$26,564
Site establishment, amenities & floor protection Labour 1 lot $3,100.00 35% $3,100 $4,185
Project management & site supervision Labour 5 wk $2,650.00 35% $13,250 $17,888
Skip bins & waste removal
Binway Waste & Skips
Subcontract 3 ea $690.00 15% $2,070 $2,380
Final builders clean & handover Labour 340 m² $4.60 35% $1,564 $2,111
Design & Documentation$6,588$8,210
Workspace design — concept, layout & finishes schedule Labour 33 hr $96.00 35% $3,168 $4,277
Building approval & certification (Certa Building Certifiers)
Certa Building Certifiers
Subcontract 1 lot $3,420.00 15% $3,420 $3,933
Partitions & Ceilings$44,696$56,799
Plasterboard partitions — 92mm steel stud, acoustic insulated, set & sanded Labour 54 lm $238.00 35% $12,852 $17,350
Suspended ceiling 1200×600 — fine fissured tile, new grid Labour 221 m² $64.00 35% $14,144 $19,094
Framed glazed office fronts with hinged doors & manifestation
Clearline Glass & Glazing
Subcontract 15 lm $1,180.00 15% $17,700 $20,355
Joinery$21,900$29,565
Reception counter — Polytec Ravine Natural Oak, Essastone top, DDA section Labour 1 ea $11,200.00 35% $11,200 $15,120
Staff kitchenette — overheads, island bench, Essastone tops Labour 4 lm $1,640.00 35% $6,560 $8,856
Storage wall with lockers & joinery doors Labour 3 lm $1,380.00 35% $4,140 $5,589
Electrical & Lighting$25,160$28,934
Electrical — power to layout, LED panel & feature lighting, switchboard upgrade
Voltline Electrical
Subcontract 340 m² $74.00 15% $25,160 $28,934
Data & Comms$3,822$4,395
Cat6A data outlets, patching & comms cabinet
Netpoint Data & Comms
Subcontract 21 pt $182.00 15% $3,822 $4,395
Mechanical (HVAC)$16,320$18,768
Mechanical — ductwork modifications, diffusers & re-balance
Airflow Mechanical Services
Subcontract 340 m² $48.00 15% $16,320 $18,768
Plumbing$6,200$7,130
Plumbing — kitchenette sink, Zip HydroTap & HWS
Pipeline Plumbing & Gas
Subcontract 1 lot $6,200.00 15% $6,200 $7,130
Floor Finishes$20,495$23,570
Interface carpet tiles — supply & lay, incl. floor prep
Floorworks Commercial Flooring
Subcontract 245 m² $61.00 15% $14,945 $17,187
Luxury vinyl plank to kitchen, breakout & wet areas
Floorworks Commercial Flooring
Subcontract 75 m² $74.00 15% $5,550 $6,383
Painting$8,211$9,443
Paint walls, ceilings & doors — Dulux Wash&Wear, 2 coats
Brushmark Painting & Decorating
Subcontract 714 m² $11.50 15% $8,211 $9,443
Furniture$18,672$23,900
Student desk 1200×600, height adjustable — Grey / white
Workspace Commercial Furniture
Furniture 60 ea $190.00 28% $11,400 $14,592
Student chair, polypropylene, stackable — Ocean blue
Buro Seating
Furniture 60 ea $62.00 28% $3,720 $4,762
Flip-top training table 1600×600 — White / castors
Workspace Commercial Furniture
Furniture 6 ea $340.00 28% $2,040 $2,611
Buro Roma task chair, fabric — Black fabric
Buro Seating
Furniture 8 ea $189.00 28% $1,512 $1,935
Acoustic Solutions$5,568$6,943
Autex Cube acoustic wall panel 12mm — Assorted
Autex Acoustics
Material 27 m² $58.00 22% $1,566 $1,911
Desk-mounted acoustic screen 1600×450 — Charcoal
Autex Acoustics
Material 30 ea $95.00 22% $2,850 $3,477
Install acoustic panels, screens & pods Labour 16 hr $72.00 35% $1,152 $1,555
Signage$3,600$4,140
Reception wall sign (3D acrylic) & glazing manifestation
SignCraft Signage
Subcontract 1 lot $3,600.00 15% $3,600 $4,140
Subtotal (ex GST)$201,216$248,361.00
GST 10%$24,836.10
Total (inc GST)$273,197.10
Client
Bernadette Kerr · bernadette@kairoscommunityc.com.au
8 Enterprise Street, Kunda Park QLD
Estimator: Marcus Reid · Quoted 12 Feb 2026 · Valid to 14 Mar 2026
Client approval

Accepted on 20 Feb 2026 — project raised.

Open project PCF-26011 →
Cost codes
Preliminaries$26,564 · 25%
Design & Documentation$8,210 · 20%
Partitions & Ceilings$56,799 · 21%
Joinery$29,565 · 26%
Electrical & Lighting$28,934 · 13%
Data & Comms$4,395 · 13%
Mechanical (HVAC)$18,768 · 13%
Plumbing$7,130 · 13%
Floor Finishes$23,570 · 13%
Painting$9,443 · 13%
Furniture$23,900 · 22%
Acoustic Solutions$6,943 · 20%
Signage$4,140 · 13%