PCF-25118 · Secure Access IT
Maroochydore head office · Level 3, 12 First Avenue, Maroochydore QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Closed On track PM Kurt Lindqvist · Site Sam Petrovic · 03 Nov 2025 → PC 13 Feb 2026 · Secure Access IT · from Q-26104 Revised contract
$348,481
$348,481 + $0 variations
Forecast cost
$281,394
▲ within budget $281,394
Forecast margin
19.3%
▲ quoted 19.3% · $67,087
Claimed to date
$348,481
100% of contract · 100% complete
Variations with client
$0
0 awaiting approval
Purchase orders & subcontracts
| Order | Supplier | Cost code | Type | Status | Required | ETA | Value | Billed |
| PO-5305 | Polytec | Joinery | Supply | Delivered | 13 Nov | 6 Nov | $6,806 | $6,806 |
| PO-5306 | Laminex Australia | Joinery | Supply | Delivered | 13 Nov | 10 Nov | $2,900 | $2,900 |
| PO-5307 | Hettich Australia | Joinery | Supply | Delivered | 13 Nov | 6 Nov | $1,584 | $1,584 |
| PO-5308 | Rondo Building Services | Partitions & Ceilings | Supply | Delivered | 18 Nov | 17 Nov | $4,824 | $4,824 |
| PO-5309 | Knauf Plasterboard | Partitions & Ceilings | Supply | Delivered | 18 Nov | 14 Nov | $4,230 | $4,230 |
| PO-5303 | B Quiet Acoustic Pods | Acoustic Solutions | Supply | Delivered | 26 Jan | 22 Jan | $19,600 | $19,600 |
| PO-5304 | Autex Acoustics | Acoustic Solutions | Supply | Delivered | 26 Jan | 22 Jan | $3,355 | $3,355 |
| PO-5301 | Workspace Commercial Furniture | Furniture | Supply | Delivered | 30 Jan | 26 Jan | $39,520 | $39,520 |
| PO-5302 | Buro Seating | Furniture | Supply | Delivered | 30 Jan | 21 Jan | $17,328 | $17,328 |
| PO-5310 | Binway Waste & Skips | Preliminaries | Subcontract | Complete | 3 Nov | 3 Nov | $2,760 | $2,677 |
| PO-5311 | Certa Building Certifiers | Design & Documentation | Subcontract | Complete | 3 Nov | 3 Nov | $3,540 | $3,434 |
| PO-5312 | Clearline Glass & Glazing | Partitions & Ceilings | Subcontract | Complete | 18 Nov | 18 Nov | $18,880 | $18,314 |
| PO-5313 | Voltline Electrical | Electrical & Lighting | Subcontract | Complete | 21 Nov | 21 Nov | $28,120 | $27,276 |
| PO-5315 | Airflow Mechanical Services | Mechanical (HVAC) | Subcontract | Complete | 24 Nov | 24 Nov | $18,240 | $17,693 |
| PO-5314 | Netpoint Data & Comms | Data & Comms | Subcontract | Complete | 4 Dec | 4 Dec | $8,736 | $8,474 |
| PO-5316 | Pipeline Plumbing & Gas | Plumbing | Subcontract | Complete | 4 Dec | 4 Dec | $6,200 | $6,014 |
| PO-5318 | Brushmark Painting & Decorating | Painting | Subcontract | Complete | 29 Dec | 29 Dec | $9,177 | $8,902 |
| PO-5317 | Floorworks Commercial Flooring | Floor Finishes | Subcontract | Complete | 12 Jan | 12 Jan | $22,930 | $22,242 |
| PO-5319 | SignCraft Signage | Signage | Subcontract | Complete | 30 Jan | 30 Jan | $3,600 | $3,492 |