Live jobs96 under way · 3 starting soon
This week14work packages running · 4 subcontracted
Needs attention3late delivery · out of sequence · double-booking
Joinery workshop peak92%w/c 21 Sep · site crew peak 81%
1 job · click a job to expand
21 Sep
This week
5 Oct
12 Oct
Joinery workshop114 h a week · 3 joiners
92%
92%
92%
66%
Site crew228 h a week · 6 carpenters & labourers
81%
51%
33%
34%
Calculated from the in-house hours on the work packages below — move a package and capacity recalculates.
Today
▸ PCF-26036 Ocean Street Brewing Co Jess · 81% complete · handover 16 Oct Now: Joinery installation, Services fit-off +2
1Site handover and establishment
✓ Site handover and establishment · done 24 Jul
2Defit, demolition and make good
✓ Defit, demolition and make good · done 6 Aug
3Services rough-in
✓ Services rough-in · done 24 Aug
4Partitions, framing and ceilings
✓ Partitions, framing and ceilings · done 7 Sep
5Joinery manufacture
✓ Joinery manufacture · done 11 Sep
6Flooring
Flooring · Floorworks
7Painting
Painting · Brushmark
8Joinery installation
Joinery installation · Prima crew
9Services fit-off
11Signage
12Furniture delivery
Furniture delivery · Prima crew
13Furniture installation
Furniture installation · Prima crew
14Final clean, defects and handover
Final clean, defects and handover · Prima crew
Click a job to see its work packages · drag a package to move it, drag its right edge to change its length · click a package to edit or reassign it.