Every live job · 21 Sep – 15 Nov 2026
Demo 02 Oct 2026
Live jobs96 under way · 3 starting soon
This week14work packages running · 4 subcontracted
Needs attention4late delivery · out of sequence · double-booking · over capacity
Joinery workshop peak110%w/c 26 Oct · site crew peak 82%
CompleteIn progressNot startedAt risk In-houseSubcontractorPO delivery
1 job · click a job to expand
21 Sep
This week
5 Oct
12 Oct
19 Oct
26 Oct
2 Nov
9 Nov
Joinery workshop114 h a week · 3 joiners
92%
92%
92%
66%
66%
110%
44%
44%
Site crew228 h a week · 6 carpenters & labourers
81%
51%
33%
34%
46%
50%
82%
72%
Calculated from the in-house hours on the work packages below — move a package and capacity recalculates.
Today
▸ PCF-26034 Nexa Engineering Kurt · 43% complete · handover 27 Nov ⚠ Subcontractor double-booked
⚠ Birtinya HQ · 43%
1Site handover and establishment Prima site crew
✓ Site handover and establishment · done 3 Aug
2Defit, demolition and make good Prima site crewafter site handover and establishment
✓ Defit, demolition and make good · done 18 Aug
3Services rough-in Voltline Electricalafter defit
✓ Services rough-in · done 11 Sep
4Partitions, framing and ceilings Prima site crewafter defit
Partitions, framing and ceilings · Prima crew
5Joinery manufacture Kunda Park workshopafter site handover and establishment
Joinery manufacture · Workshop
6Flooring Floorworks Commercial Flooringafter partitions
Flooring · Floorworks
7Painting Brushmark Painting & Decoratingafter partitions
⚠ Painting · Brushmark
8Joinery installation Prima site crewafter joinery manufacture
Joinery installation · Prima crew
9Services fit-off Voltline Electricalafter joinery installation
Services fit-off · Voltline
10Glazing and doors Clearline Glass & Glazingafter partitions
Glazing and doors · Clearline
11Signage SignCraft Signageafter painting
Signage · SignCraft
12Furniture delivery Prima site crewafter flooring
Furniture delivery · Prima crew
13Furniture installation Prima site crewafter furniture delivery
Furniture installation · Prima crew
14Final clean, defects and handover Prima site crewafter furniture installation
Final clean, defects and handover · from 24 Nov →
Click a job to see its work packages · drag a package to move it, drag its right edge to change its length · click a package to edit or reassign it.