Live jobs96 under way · 3 starting soon
This week14work packages running · 4 subcontracted
Needs attention3late delivery · out of sequence · double-booking
Joinery workshop peak92%w/c 21 Sep · site crew peak 81%
1 job · click a job to expand
21 Sep
This week
5 Oct
12 Oct
Joinery workshop114 h a week · 3 joiners
92%
92%
92%
66%
Site crew228 h a week · 6 carpenters & labourers
81%
51%
33%
34%
Calculated from the in-house hours on the work packages below — move a package and capacity recalculates.
Today
▸ PCF-26034 Nexa Engineering Kurt · 43% complete · handover 27 Nov ⚠ Subcontractor double-booked
1Site handover and establishment
✓ Site handover and establishment · done 3 Aug
2Defit, demolition and make good
✓ Defit, demolition and make good · done 18 Aug
3Services rough-in
✓ Services rough-in · done 11 Sep
4Partitions, framing and ceilings
Partitions, framing and ceilings · Prima crew
5Joinery manufacture
6Flooring
7Painting
8Joinery installation
Joinery installation · from 2 Nov →
9Services fit-off
Services fit-off · from 10 Nov →
10Glazing and doors
11Signage
Signage · from 4 Nov →
12Furniture delivery
Furniture delivery · from 5 Nov →
13Furniture installation
Furniture installation · from 10 Nov →
14Final clean, defects and handover
Final clean, defects and handover · from 24 Nov →
Click a job to see its work packages · drag a package to move it, drag its right edge to change its length · click a package to edit or reassign it.