Quote Q-26113

Cafe on George — dining & bar
Demo 02 Oct 2026
Quote total (ex GST)
$216,758
$238,433.80 inc GST
Estimated cost
$173,637
27 lines · 13 cost codes
Margin
19.9%
$43,122 gross profit
Mix
Furniture Material Labour Subcontract
Estimate Accepted
DescriptionTypeQtyUnit costMarkupCostSell
Preliminaries$13,244$17,466
Site establishment, amenities & floor protection Labour 1 lot $2,350.00 35% $2,350 $3,173
Project management & site supervision Labour 3 wk $2,650.00 35% $7,950 $10,733
Skip bins & waste removal
Coastal Skip Bins
Subcontract 3 ea $690.00 15% $2,070 $2,380
Final builders clean & handover Labour 190 m² $4.60 35% $874 $1,180
Design & Documentation$5,466$6,786
Workspace design — concept, layout & finishes schedule Labour 26 hr $96.00 35% $2,496 $3,370
Building approval & certification (Sunshine Coast Certifiers)
Sunshine Coast Certifiers
Subcontract 1 lot $2,970.00 15% $2,970 $3,416
Demolition & Make Good$4,682$6,321
Strip out partitions, ceilings & services to agreed scope Labour 67 m² $26.00 35% $1,742 $2,352
Make good slab, walls & penetrations Labour 1 lot $2,940.00 35% $2,940 $3,969
Partitions & Ceilings$11,506$15,534
Plasterboard partitions — 92mm steel stud, acoustic insulated, set & sanded Labour 15 lm $238.00 35% $3,570 $4,820
Suspended ceiling 1200×600 — fine fissured tile, new grid Labour 124 m² $64.00 35% $7,936 $10,714
Joinery$41,330$55,796
Bar counter 6.2m — spotted gum battens, stone top, under-bar fridges cavities Labour 1 ea $24,800.00 35% $24,800 $33,480
Back bar shelving & tap wall joinery Labour 5 lm $1,650.00 35% $8,250 $11,138
Banquette seating, upholstered, timber base Labour 9 lm $920.00 35% $8,280 $11,178
Electrical & Lighting$17,480$20,102
Electrical — power to layout, LED panel & feature lighting, switchboard upgrade
Coastline Electrical Contracting
Subcontract 190 m² $92.00 15% $17,480 $20,102
Mechanical (HVAC)$12,920$14,858
Mechanical — ductwork modifications, diffusers & re-balance
Maroochy Air Conditioning
Subcontract 190 m² $68.00 15% $12,920 $14,858
Plumbing$18,400$21,160
Plumbing — bar sinks, glass washer, floor wastes, grease arrestor connection
Nambour Plumbing Services
Subcontract 1 lot $18,400.00 15% $18,400 $21,160
Floor Finishes$12,160$13,984
Interface carpet tiles — supply & lay, incl. floor prep
Hinterland Flooring Co.
Subcontract 38 m² $61.00 15% $2,318 $2,666
Luxury vinyl plank to kitchen, breakout & wet areas
Hinterland Flooring Co.
Subcontract 133 m² $74.00 15% $9,842 $11,318
Painting$4,589$5,277
Paint walls, ceilings & doors — Dulux Wash&Wear, 2 coats
Buderim Painting Group
Subcontract 399 m² $11.50 15% $4,589 $5,277
Furniture$15,420$19,738
Café table 800×800 — Oak / black base
Workspace Commercial Furniture
Furniture 14 ea $260.00 28% $3,640 $4,659
Meeting chair, 4-leg, upholstered — Ocean blue
Buro Seating
Furniture 40 ea $168.00 28% $6,720 $8,602
Bar leaner 3000×600, 1050 high — Spotted gum
Workspace Commercial Furniture
Furniture 2 ea $1,450.00 28% $2,900 $3,712
Kitchen stool, oak seat, 750 high — Natural oak / black
Buro Seating
Furniture 18 ea $120.00 28% $2,160 $2,765
Acoustic Solutions$8,640$10,766
Acoustic ceiling baffle 1200×300 — Charcoal
Autex Acoustics
Material 60 ea $64.00 22% $3,840 $4,685
Autex Lanes acoustic ceiling panel — Sydney Grey
Autex Acoustics
Material 24 m² $128.00 22% $3,072 $3,748
Install ceiling baffles & Lanes panels Labour 24 hr $72.00 35% $1,728 $2,333
Signage$7,800$8,970
Illuminated venue sign, menu boards & window graphics
SignCraft Sunshine Coast
Subcontract 1 lot $7,800.00 15% $7,800 $8,970
Subtotal (ex GST)$173,637$216,758.00
GST 10%$21,675.80
Total (inc GST)$238,433.80
Client
Luca Romano · luca@cafeongeorge.com.au
Level 14, 300 Adelaide Street, Brisbane City QLD
Estimator: Marcus Reid · Quoted 23 Mar 2026 · Valid to 22 Apr 2026
Client approval

Accepted on 31 Mar 2026 — project raised.

Open project PCF-26019 →
Cost codes
Preliminaries$17,466 · 24%
Design & Documentation$6,786 · 19%
Demolition & Make Good$6,321 · 26%
Partitions & Ceilings$15,534 · 26%
Joinery$55,796 · 26%
Electrical & Lighting$20,102 · 13%
Mechanical (HVAC)$14,858 · 13%
Plumbing$21,160 · 13%
Floor Finishes$13,984 · 13%
Painting$5,277 · 13%
Furniture$19,738 · 22%
Acoustic Solutions$10,766 · 20%
Signage$8,970 · 13%