PCF-26004 · MGA Insurance Group

Level 2 refurbishment · 4/58 Aerodrome Road, Maroochydore QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Closed On track PM Kurt Lindqvist · Site Dean O'Connell · 02 Feb 2026 → PC 22 May 2026 · MGA Insurance Group · from Q-26107
Revised contract
$587,187
$579,524 + $7,663 variations
Forecast cost
$475,499
▼ $2,620 over budget
Forecast margin
19.0%
▼ quoted 19.5% · $111,688
Claimed to date
$587,187
100% of contract · 100% complete
Variations with client
$0
0 awaiting approval
Actual costs posted$475,001
DateCost codeTypeSourceDescriptionAmount
22 MaySignageSubcontractPO-5338 · claim 4SignCraft Signage — progress claim 4$562.37
22 MayPaintingSubcontractPO-5337 · claim 4Brushmark Painting & Decorating — progress claim 4$2,086.64
22 MayFloor FinishesSubcontractPO-5336 · claim 4Floorworks Commercial Flooring — progress claim 4$6,472.87
22 MayPlumbingSubcontractPO-5335 · claim 4Pipeline Plumbing & Gas — progress claim 4$668.34
22 MayMechanical (HVAC)SubcontractPO-5334 · claim 4Airflow Mechanical Services — progress claim 4$7,834.78
22 MayData & CommsSubcontractPO-5333 · claim 4Netpoint Data & Comms — progress claim 4$3,793.10
22 MayElectrical & LightingSubcontractPO-5332 · claim 4Voltline Electrical — progress claim 4$10,690.33
22 MayPartitions & CeilingsSubcontractPO-5331 · claim 4Clearline Glass & Glazing — progress claim 4$5,729.61
22 MayDesign & DocumentationSubcontractPO-5330 · claim 4Certa Building Certifiers — progress claim 4$462.79
22 MayPreliminariesSubcontractPO-5329 · claim 4Binway Waste & Skips — progress claim 4$793.47
5 MayFurnitureLabourV-26004-02Variation works — Upgrade boardroom to Blackbutt veneer table$1,450.00
4 MayFurnitureMaterialPO-5321Buro Seating — delivery$34,516.00
4 MayFurnitureMaterialPO-5320Workspace Commercial Furniture — delivery$61,625.00
27 AprAcoustic SolutionsMaterialPO-5323Autex Acoustics — delivery$5,597.00
24 AprSignageSubcontractPO-5338 · claim 3SignCraft Signage — progress claim 3$388.37
24 AprPaintingSubcontractPO-5337 · claim 3Brushmark Painting & Decorating — progress claim 3$2,716.29
24 AprFloor FinishesSubcontractPO-5336 · claim 3Floorworks Commercial Flooring — progress claim 3$3,951.11
24 AprPlumbingSubcontractPO-5335 · claim 3Pipeline Plumbing & Gas — progress claim 3$780.80
24 AprMechanical (HVAC)SubcontractPO-5334 · claim 3Airflow Mechanical Services — progress claim 3$5,210.50
24 AprData & CommsSubcontractPO-5333 · claim 3Netpoint Data & Comms — progress claim 3$1,894.12
24 AprElectrical & LightingSubcontractPO-5332 · claim 3Voltline Electrical — progress claim 3$6,325.30
24 AprPartitions & CeilingsSubcontractPO-5331 · claim 3Clearline Glass & Glazing — progress claim 3$3,671.19
24 AprDesign & DocumentationSubcontractPO-5330 · claim 3Certa Building Certifiers — progress claim 3$559.36
24 AprPreliminariesSubcontractPO-5329 · claim 3Binway Waste & Skips — progress claim 3$650.66
23 AprFurnitureLabourV-26004-01Variation works — Additional sit-stand desks ×6 for new hires$4,680.00
22 AprAcoustic SolutionsMaterialPO-5322B Quiet Acoustic Pods — delivery$46,400.00
27 MarAcoustic SolutionsLabourTimesheets w/e 27/03Site labour$218.16
27 MarJoineryLabourTimesheets w/e 27/03Workshop & install labour$2,638.27
27 MarPartitions & CeilingsLabourTimesheets w/e 27/03Site labour$4,306.69
27 MarDemolition & Make GoodLabourTimesheets w/e 27/03Site labour$1,391.78
27 MarDesign & DocumentationLabourTimesheets w/e 27/03Site labour$569.64
27 MarPreliminariesLabourTimesheets w/e 27/03PM & supervision$3,927.15
27 MarSignageSubcontractPO-5338 · claim 2SignCraft Signage — progress claim 2$606.51
27 MarPaintingSubcontractPO-5337 · claim 2Brushmark Painting & Decorating — progress claim 2$4,093.57
27 MarFloor FinishesSubcontractPO-5336 · claim 2Floorworks Commercial Flooring — progress claim 2$7,602.98
27 MarPlumbingSubcontractPO-5335 · claim 2Pipeline Plumbing & Gas — progress claim 2$1,962.05
27 MarMechanical (HVAC)SubcontractPO-5334 · claim 2Airflow Mechanical Services — progress claim 2$5,847.08
27 MarData & CommsSubcontractPO-5333 · claim 2Netpoint Data & Comms — progress claim 2$2,983.07
27 MarElectrical & LightingSubcontractPO-5332 · claim 2Voltline Electrical — progress claim 2$9,621.51
27 MarPartitions & CeilingsSubcontractPO-5331 · claim 2Clearline Glass & Glazing — progress claim 2$5,843.56
27 MarDesign & DocumentationSubcontractPO-5330 · claim 2Certa Building Certifiers — progress claim 2$1,517.25
27 MarPreliminariesSubcontractPO-5329 · claim 2Binway Waste & Skips — progress claim 2$634.43
20 MarAcoustic SolutionsLabourTimesheets w/e 20/03Site labour$218.16
20 MarJoineryLabourTimesheets w/e 20/03Workshop & install labour$2,638.30
20 MarPartitions & CeilingsLabourTimesheets w/e 20/03Site labour$4,306.69
20 MarDemolition & Make GoodLabourTimesheets w/e 20/03Site labour$1,391.78
20 MarDesign & DocumentationLabourTimesheets w/e 20/03Site labour$569.64
20 MarPreliminariesLabourTimesheets w/e 20/03PM & supervision$3,927.13
13 MarAcoustic SolutionsLabourTimesheets w/e 13/03Site labour$218.16
13 MarJoineryLabourTimesheets w/e 13/03Workshop & install labour$2,638.30
13 MarPartitions & CeilingsLabourTimesheets w/e 13/03Site labour$4,306.69
13 MarDemolition & Make GoodLabourTimesheets w/e 13/03Site labour$1,391.78
13 MarDesign & DocumentationLabourTimesheets w/e 13/03Site labour$569.64
13 MarPreliminariesLabourTimesheets w/e 13/03PM & supervision$3,927.13
6 MarAcoustic SolutionsLabourTimesheets w/e 06/03Site labour$218.16
6 MarJoineryLabourTimesheets w/e 06/03Workshop & install labour$2,638.30
6 MarPartitions & CeilingsLabourTimesheets w/e 06/03Site labour$4,306.69
6 MarDemolition & Make GoodLabourTimesheets w/e 06/03Site labour$1,391.78
6 MarDesign & DocumentationLabourTimesheets w/e 06/03Site labour$569.64
6 MarPreliminariesLabourTimesheets w/e 06/03PM & supervision$3,927.13
27 FebAcoustic SolutionsLabourTimesheets w/e 27/02Site labour$218.16
27 FebJoineryLabourTimesheets w/e 27/02Workshop & install labour$2,638.30
27 FebPartitions & CeilingsLabourTimesheets w/e 27/02Site labour$4,306.69
27 FebDemolition & Make GoodLabourTimesheets w/e 27/02Site labour$1,391.78
27 FebDesign & DocumentationLabourTimesheets w/e 27/02Site labour$569.64
27 FebPreliminariesLabourTimesheets w/e 27/02PM & supervision$3,927.13
27 FebSignageSubcontractPO-5338 · claim 1SignCraft Signage — progress claim 1$2,078.75
27 FebPaintingSubcontractPO-5337 · claim 1Brushmark Painting & Decorating — progress claim 1$5,982.32
27 FebFloor FinishesSubcontractPO-5336 · claim 1Floorworks Commercial Flooring — progress claim 1$19,034.99
27 FebPlumbingSubcontractPO-5335 · claim 1Pipeline Plumbing & Gas — progress claim 1$2,850.81
27 FebMechanical (HVAC)SubcontractPO-5334 · claim 1Airflow Mechanical Services — progress claim 1$10,680.44
27 FebData & CommsSubcontractPO-5333 · claim 1Netpoint Data & Comms — progress claim 1$5,300.03
27 FebElectrical & LightingSubcontractPO-5332 · claim 1Voltline Electrical — progress claim 1$18,954.26
27 FebPartitions & CeilingsSubcontractPO-5331 · claim 1Clearline Glass & Glazing — progress claim 1$13,358.84
27 FebDesign & DocumentationSubcontractPO-5330 · claim 1Certa Building Certifiers — progress claim 1$1,732.90
27 FebPreliminariesSubcontractPO-5329 · claim 1Binway Waste & Skips — progress claim 1$1,405.94
20 FebAcoustic SolutionsLabourTimesheets w/e 20/02Site labour$218.16
20 FebJoineryLabourTimesheets w/e 20/02Workshop & install labour$2,638.30
20 FebPartitions & CeilingsLabourTimesheets w/e 20/02Site labour$4,306.69
20 FebDemolition & Make GoodLabourTimesheets w/e 20/02Site labour$1,391.78
20 FebDesign & DocumentationLabourTimesheets w/e 20/02Site labour$569.64
20 FebPreliminariesLabourTimesheets w/e 20/02PM & supervision$3,927.13
16 FebPartitions & CeilingsMaterialPO-5327Rondo Building Services — materials delivered$7,765.00
13 FebAcoustic SolutionsLabourTimesheets w/e 13/02Site labour$218.16
13 FebJoineryLabourTimesheets w/e 13/02Workshop & install labour$2,638.30
13 FebPartitions & CeilingsLabourTimesheets w/e 13/02Site labour$4,306.69
13 FebDemolition & Make GoodLabourTimesheets w/e 13/02Site labour$1,391.78
13 FebDesign & DocumentationLabourTimesheets w/e 13/02Site labour$569.64
13 FebPreliminariesLabourTimesheets w/e 13/02PM & supervision$3,927.13
10 FebPartitions & CeilingsMaterialPO-5328Knauf Plasterboard — materials delivered$6,795.00
9 FebJoineryMaterialPO-5325Laminex Australia — materials delivered$2,900.00
9 FebJoineryMaterialPO-5324Polytec — materials delivered$9,334.00
6 FebAcoustic SolutionsLabourTimesheets w/e 06/02Site labour$218.16
6 FebJoineryLabourTimesheets w/e 06/02Workshop & install labour$2,638.30
6 FebPartitions & CeilingsLabourTimesheets w/e 06/02Site labour$4,306.69
6 FebDemolition & Make GoodLabourTimesheets w/e 06/02Site labour$1,391.78
6 FebDesign & DocumentationLabourTimesheets w/e 06/02Site labour$569.64
6 FebPreliminariesLabourTimesheets w/e 06/02PM & supervision$3,927.13
5 FebJoineryMaterialPO-5326Hettich Australia — materials delivered$2,192.10