PCF-26041 · Tidewater Property Group

end-of-lease make good · Level 1, 33 Brisbane Road, Mooloolaba QLD
Xero connected · last sync 9:14am Demo 02 Oct 2026
Practical Completion On track PM Kurt Lindqvist · Site Dean O'Connell · 31 Aug 2026 → PC 25 Sep 2026 · Tidewater Property Group · from Q-26131
Revised contract
$59,578
$57,203 + $2,375 variations
Forecast cost
$46,709
▲ within budget $46,709
Forecast margin
21.6%
▼ quoted 21.7% · $12,870
Claimed to date
$58,900
99% of contract · 99% complete
Variations with client
$0
0 awaiting approval
Budget vs actual by cost code Click a % to update progress · committed = issued orders not yet billed
Cost codeContractVariationsBudgetActualCommittedForecastVariance% complete
Preliminaries $22,598 — $17,046 $15,870 $143 $17,046 —
98%
Demolition & Make Good $18,082 $2,375 $15,294 $14,624 — $15,294 —
100%
Floor Finishes $7,914 — $6,882 $6,538 $344 $6,882 —
100%
Painting $8,609 — $7,487 $7,112 $374 $7,487 —
100%
Total$57,203$2,375$46,709 $44,144$861$46,709 —99%